United States βΊ Grid βΊ Interconnection queues βΊ Indiana
ONSHORE WIND Β· MISOOnshore wind project G952, Tipton County
Onshore wind project G952, Tipton County is a 100 MW onshore wind request withdrawn in the MISO interconnection queue, in Tipton County, Indiana.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2008 (completed)
- Withdrawn / abandonedDec 2010 (project stopped here)
- ConsentedDec 2010 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G952
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Kokomo - Noblesville 230 kV
- Location
- Tipton County, Indiana
- Technology
- Wind: 100 MW
- Total requested
- 100 MW
- Study phase
- SPA - SIS
- Queue status
- Withdrawn
- Entered queue
- 15 January 2008
- Agreement signed
- 28 December 2010
- Proposed online date
- February 2011
- Withdrawn
- December 2010
Location
Marker shows the centre of Tipton County; the queue data does not give exact sites.
Other requests in Tipton County
- Battery storage project J2232, Tipton CountyBattery storage Β· 100 MW Β· in study
- Solar project J2177, Tipton CountySolar Β· 67.0 MW Β· in study
- Onshore wind project G923, Tipton CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project J054, Tipton CountyOnshore wind Β· 198 MW Β· withdrawn
- Solar project J1625, Tipton CountySolar Β· 150 MW Β· withdrawn
- Solar project J1765, Tipton CountySolar Β· 93.2 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem