United States βΊ Grid βΊ Interconnection queues βΊ Indiana
SOLAR Β· MISOSolar project J3196, Starke County
Solar project J3196, Starke County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Starke County, Indiana, connecting to NORTHERN INDIANA PUBLIC SERVICE COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedFeb 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3196
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN INDIANA PUBLIC SERVICE COMPANY
- Connection point (POI)
- Burr Oak to East Winamac 138 kV
- Location
- Starke County, Indiana
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 15 September 2022
- Proposed online date
- October 2025
- Withdrawn
- February 2023
Location
Marker shows the centre of Starke County; the queue data does not give exact sites.
Other requests in Starke County
- Solar project AG2-245, Starke CountySolar Β· 210 MW Β· in study
- Solar project J1684, Starke CountySolar Β· 200 MW Β· in study
- Solar project J2847, Starke CountySolar Β· 180 MW Β· in study
- Solar project J3207, Starke CountySolar Β· 100 MW Β· in study
- Mammoth North Solar ProjectSolar Β· 300 MW Β· built
- Mammoth North Solar ProjectSolar Β· 100 MW Β· built
- Solar + storage project J2959, Starke CountySolar + storage Β· 200 MW Β· withdrawn
- Solar project J1342, Starke CountySolar Β· 99.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem