United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in the USA — page 77
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project GEN-2014-008, Lea County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project GI-2010-16, Kit Carson County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project GI-72, New Madrid County Solar |
300 MW | Withdrawn / abandoned |
| Solar project J2310, Beauregard Parish County Solar |
300 MW | Withdrawn / abandoned |
| EI Steinway 2.1 Offshore wind · Beacon Wind LLC |
300 MW | Withdrawn / abandoned |
| Onshore wind project G728, Steele County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2022-192, Ford County Onshore wind |
300 MW | Withdrawn / abandoned |
| Battery storage project J2497, Jefferson County Battery storage |
300 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2008-017, Scott County Onshore wind |
300 MW | Withdrawn / abandoned |
| Flat Creek Storage Battery storage · SED NY Holdings LLC |
300 MW | Withdrawn / abandoned |
| Onshore wind project MPC04100, Grand Forks County Onshore wind |
300 MW | Withdrawn / abandoned |
| Battery storage project AG1-199, Lucas County Battery storage · Occasio Power Management LLC |
300 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2016-084, Lea County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar + storage project IC-845, Mobile County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project C3-133, Box Elder County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project Q516, Pinal County Solar + storage |
300 MW | Withdrawn / abandoned |
| Battery storage project J4171, Racine County Battery storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project Q69, San Bernardino County Solar + storage |
300 MW | Withdrawn / abandoned |
| Brazoria Texas Peakers Gas · LS Power Associates, LP |
300 MW | Withdrawn / abandoned |
| Onshore wind project W3-013, Miami County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2016-081, Yoakum County Onshore wind |
300 MW | Withdrawn / abandoned |
| Battery storage project 622, Desoto County Battery storage · FPL |
300 MW | Withdrawn / abandoned |
| Solar + storage project Company OH, Lander County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar project 534, Jerome County Solar |
300 MW | Withdrawn / abandoned |
| Onshore wind project J1456, Sheridan County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project GEN-2022-022, Chaves County Solar |
300 MW | Withdrawn / abandoned |
| Blanco Canyon Wind Onshore wind · Blanco Canyon Wind Development |
300 MW | Withdrawn / abandoned |
| Gas project H08_W66 Gas |
300 MW | Withdrawn / abandoned |
| Battery storage project AH1-736, Baltimore County Battery storage · Carroll Island BESS I LLC |
300 MW | Withdrawn / abandoned |
| Solar + storage project Company 188, Clark County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar project GEN-2022-056, Lamb County Solar |
300 MW | Withdrawn / abandoned |
| Solar + storage project 658, Power County Solar + storage |
300 MW | Withdrawn / abandoned |
| Bright Stalk WF Onshore wind |
300 MW | Withdrawn / abandoned |
| Gas project 24, Lane County Gas |
300 MW | Withdrawn / abandoned |
| Solar project GI-76, Pemiscot County Solar |
300 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2008-019, Dewey County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar + storage project C4-039, Franklin County Solar + storage |
300 MW | Withdrawn / abandoned |
| CWW 300 Wind Onshore wind · Diamond Generating Corporation |
300 MW | Withdrawn / abandoned |
| Solar + storage project 1171, Converse County Solar + storage |
300 MW | Withdrawn / abandoned |
| Onshore wind project 168, Cochise County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project PIS029, Utah County Onshore wind |
300 MW | Withdrawn / abandoned |
| Cedar Hills Energy LLC Gas · Cedar Hills Energy LLC |
300 MW | Withdrawn / abandoned |
| Solar + storage project C4-111, Iron County Solar + storage |
300 MW | Withdrawn / abandoned |
| Enn Mojave Power 4 Other |
300 MW | Withdrawn / abandoned |
| Onshore wind project J1666, Ingham County Onshore wind |
300 MW | Withdrawn / abandoned |
| Sugar Loaf Energy Storage II Battery storage · Hambletonian Energy Storage II LLC |
300 MW | Withdrawn / abandoned |
| Onshore wind project GI-2010-3, Huerfano County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project J3570, Cross County Solar |
300 MW | Withdrawn / abandoned |
| Battery storage project Company 199, Clark County Battery storage |
300 MW | Withdrawn / abandoned |
| Onshore wind project GI-2007-4, Weld County Onshore wind |
300 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)