United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 77

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 77 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2014-008, Lea County
Onshore wind
300 MWWithdrawn / abandoned Lea, NMSPP Mar 2014target 2018
Onshore wind project GI-2010-16, Kit Carson County
Onshore wind
300 MWWithdrawn / abandoned Kit Carson, COWest Nov 2010target 2014
Solar project GI-72, New Madrid County
Solar
300 MWWithdrawn / abandoned New Madrid, MOSoutheast Nov 2018target 2021
Solar project J2310, Beauregard Parish County
Solar
300 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2021target 2024
EI Steinway 2.1
Offshore wind · Beacon Wind LLC
300 MWWithdrawn / abandoned Queens, NYNYISO Jun 2021
Onshore wind project G728, Steele County
Onshore wind
300 MWWithdrawn / abandoned Steele, MNMISO Jan 2007target 2008
Onshore wind project GEN-2022-192, Ford County
Onshore wind
300 MWWithdrawn / abandoned Ford, KSSPP Feb 2023target 2027
Battery storage project J2497, Jefferson County
Battery storage
300 MWWithdrawn / abandoned Jefferson, ILMISO Sep 2022target 2026
Onshore wind project GEN-2008-017, Scott County
Onshore wind
300 MWWithdrawn / abandoned Scott, KSSPP Mar 20082017
Flat Creek Storage
Battery storage · SED NY Holdings LLC
300 MWWithdrawn / abandoned Montgomery, NYNYISO May 2023
Onshore wind project MPC04100, Grand Forks County
Onshore wind
300 MWWithdrawn / abandoned Grand Forks, NDMISO Apr 2019target 2023
Battery storage project AG1-199, Lucas County
Battery storage · Occasio Power Management LLC
300 MWWithdrawn / abandoned Lucas, OHPJM Sep 2020target 2023
Onshore wind project GEN-2016-084, Lea County
Onshore wind
300 MWWithdrawn / abandoned Lea, NMSPP Jun 2016target 2019
Solar + storage project IC-845, Mobile County
Solar + storage
300 MWWithdrawn / abandoned Mobile, ALSoutheast Jan 2020
Solar + storage project C3-133, Box Elder County
Solar + storage
300 MWWithdrawn / abandoned Box Elder, UTWest May 2023target 2027
Solar + storage project Q516, Pinal County
Solar + storage
300 MWWithdrawn / abandoned Pinal, AZWest Mar 2023target 2027
Battery storage project J4171, Racine County
Battery storage
300 MWWithdrawn / abandoned Racine, WIMISO Oct 2025target 2029
Solar + storage project Q69, San Bernardino County
Solar + storage
300 MWWithdrawn / abandoned San Bernardino, CAWest Apr 2019target 2022
Brazoria Texas Peakers
Gas · LS Power Associates, LP
300 MWWithdrawn / abandoned ERCOT Aug 2008target 2050
Onshore wind project W3-013, Miami County
Onshore wind
300 MWWithdrawn / abandoned Miami, OHPJM Aug 2010target 2014
Onshore wind project GEN-2016-081, Yoakum County
Onshore wind
300 MWWithdrawn / abandoned Yoakum, TXSPP Jun 2016target 2019
Battery storage project 622, Desoto County
Battery storage · FPL
300 MWWithdrawn / abandoned Desoto, FLSoutheast Jan 2024target 2030
Solar + storage project Company OH, Lander County
Solar + storage
300 MWWithdrawn / abandoned Lander, NVWest Jan 2023target 2028
Solar project 534, Jerome County
Solar
300 MWWithdrawn / abandoned Jerome, IDWest May 2018
Onshore wind project J1456, Sheridan County
Onshore wind
300 MWWithdrawn / abandoned Sheridan, NDMISO Apr 2019target 2023
Solar project GEN-2022-022, Chaves County
Solar
300 MWWithdrawn / abandoned Chaves, NMSPP Jun 20222025
Blanco Canyon Wind
Onshore wind · Blanco Canyon Wind Development
300 MWWithdrawn / abandoned ERCOT Jul 2011target 2050
Gas project H08_W66
Gas
300 MWWithdrawn / abandoned WVPJM Nov 2001target 2005
Battery storage project AH1-736, Baltimore County
Battery storage · Carroll Island BESS I LLC
300 MWWithdrawn / abandoned Baltimore, MDPJM target 2028
Solar + storage project Company 188, Clark County
Solar + storage
300 MWWithdrawn / abandoned Clark, NVWest Sep 2019target 2022
Solar project GEN-2022-056, Lamb County
Solar
300 MWWithdrawn / abandoned Lamb, TXSPP Jun 20222025
Solar + storage project 658, Power County
Solar + storage
300 MWWithdrawn / abandoned Power, IDWest Jun 2022target 2024
Bright Stalk WF
Onshore wind
300 MWWithdrawn / abandoned Livingston, ILPJM May 2005target 2013
Gas project 24, Lane County
Gas
300 MWWithdrawn / abandoned Lane, ORWest Jun 2003target 2007
Solar project GI-76, Pemiscot County
Solar
300 MWWithdrawn / abandoned Pemiscot, MOSoutheast Nov 2018target 2021
Onshore wind project GEN-2008-019, Dewey County
Onshore wind
300 MWWithdrawn / abandoned Dewey, OKSPP Mar 2008target 2012
Solar + storage project C4-039, Franklin County
Solar + storage
300 MWWithdrawn / abandoned Franklin, IDWest May 2024target 2028
CWW 300 Wind
Onshore wind · Diamond Generating Corporation
300 MWWithdrawn / abandoned Erie, NYNYISO Apr 2019
Solar + storage project 1171, Converse County
Solar + storage
300 MWWithdrawn / abandoned Converse, WYWest Oct 2019target 2021
Onshore wind project 168, Cochise County
Onshore wind
300 MWWithdrawn / abandoned Cochise, AZWest Apr 2024target 2030
Onshore wind project PIS029, Utah County
Onshore wind
300 MWWithdrawn / abandoned Utah, UTWest Mar 2023target 2027
Cedar Hills Energy LLC
Gas · Cedar Hills Energy LLC
300 MWWithdrawn / abandoned King, WAWest May 2001target 2004
Solar + storage project C4-111, Iron County
Solar + storage
300 MWWithdrawn / abandoned Iron, UTWest May 2024target 2029
Enn Mojave Power 4
Other
300 MWWithdrawn / abandoned Clark, NVCAISO Apr 2012target 2016
Onshore wind project J1666, Ingham County
Onshore wind
300 MWWithdrawn / abandoned Ingham, MIMISO Jun 2020target 2023
Sugar Loaf Energy Storage II
Battery storage · Hambletonian Energy Storage II LLC
300 MWWithdrawn / abandoned Orange, NYNYISO Oct 2024
Onshore wind project GI-2010-3, Huerfano County
Onshore wind
300 MWWithdrawn / abandoned Huerfano, COWest Feb 2010target 2013
Solar project J3570, Cross County
Solar
300 MWWithdrawn / abandoned Cross, ARMISO Apr 2024target 2028
Battery storage project Company 199, Clark County
Battery storage
300 MWWithdrawn / abandoned Clark, NVWest Sep 2021target 2025
Onshore wind project GI-2007-4, Weld County
Onshore wind
300 MWWithdrawn / abandoned Weld, COWest Mar 2007target 2013
Page 77 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)