United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 61
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project AA1-140, Worcester County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project AE1-231, Charles County Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Solar project AH1-161, Mercer County Solar |
20.0 MW | Withdrawn / abandoned |
| Fayetteville Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project AH1-095, Huron County Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Solar project AF1-139, Wayne County Solar |
20.0 MW | Withdrawn / abandoned |
| Other project U2-101, Lee County Other |
20.0 MW | Withdrawn / abandoned |
| Solar project AG1-032, James City County Solar |
20.0 MW | Withdrawn / abandoned |
| Yorktown 3 Other |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-278, Fayette County Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project T169, Cape May County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-143, Clarion County Solar · CP McCall Road LLC |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AE1-115, Salem County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar project W1-128, Warren County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AE2-119, Adams County Solar |
20.0 MW | Withdrawn / abandoned |
| IRL Landfill Solar Project Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AH1-407, Northumberland County Solar |
20.0 MW | Withdrawn / abandoned |
| Perryman Solar Farm Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-668, Clearfield County Solar · Du Bois PV I, LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AH1-379, Pulaski County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AC2-007, Boone County Solar |
20.0 MW | Withdrawn / abandoned |
| Cove Creek Solar Project Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AH1-573, Marion County Solar · Swamp Fox Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Battery storage project T187, New Castle County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar project W2-098, Adams County Solar |
20.0 MW | Withdrawn / abandoned |
| ASD Carmen PA2 Solar Solar · ASD Carmen PA2 Solar LLC |
20.0 MW | Withdrawn / abandoned |
| South Anna Unit 1 Gas |
20.0 MW | Withdrawn / abandoned |
| Solar project AH2-016, Somerset County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AG1-173, Surry County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project W3-037, Wicomico County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project W1-070, Wicomico County Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AG1-256, Accomack County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar project AH1-185, Isle Of Wight County Solar · Prairie Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AA1-126, Brown County Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AF1-281, Lee County Battery storage · Deriva Energy Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Beckett ProjectWoodstown Project Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AB2-192, Accomack County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AH1-169, Accomack County Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project X4-014, Northampton County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project AH1-382, Mercer County Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Solar project AC1-009, Accomack County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AH2-004, Halifax County Solar |
20.0 MW | Withdrawn / abandoned |
| McKean Solar 2 - 20 MW Solar · McKean County Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project X1-016, Salem County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AD1-049, Culpeper County Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AB1-073, Delaware County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar project AF2-340, Adams County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Y1-073, Tyrrell County Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AE2-294, Dauphin County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AG1-290, Baltimore County Battery storage |
20.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)