SOLAR Β· PJM

Solar project AF2-340, Adams County

Solar project AF2-340, Adams County is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Adams County, Pennsylvania, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2020 (completed)
  2. Withdrawn / abandonedApr 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AF2-340
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Location
Adams County, Pennsylvania
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
31 March 2020
Proposed online date
December 2023
Withdrawn
April 2020

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Adams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem