Solar + storage project AH1-382, Mercer County

Solar + storage project AH1-382, Mercer County is a 20.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Mercer County, Kentucky, connecting to EKPC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-382
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
EKPC
Connection point (POI)
Van Arsdell 69 kV
Location
Mercer County, Kentucky
Technology
Solar: 20.0 MW Β· Battery
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
10 September 2021
Proposed online date
March 2025
Withdrawn
December 2024

Location

Marker shows the centre of Mercer County; the queue data does not give exact sites.

Power plants in Kentucky Β· Transmission lines in Kentucky

Other requests in Mercer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem