SOLAR + STORAGE Β· PJMSolar + storage project AH1-382, Mercer County
Solar + storage project AH1-382, Mercer County is a 20.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Mercer County, Kentucky, connecting to EKPC.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2021 (completed)
- Withdrawn / abandonedDec 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-382
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Connection point (POI)
- Van Arsdell 69 kV
- Location
- Mercer County, Kentucky
- Technology
- Solar: 20.0 MW Β· Battery
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 10 September 2021
- Proposed online date
- March 2025
- Withdrawn
- December 2024
Location
Marker shows the centre of Mercer County; the queue data does not give exact sites.
Other requests in Mercer County
- Gas project LGE-GIS-2023-002, Mercer CountyGas Β· 660 MW Β· agreement signed
- Solar project LGE-GIS-2019-025, Mercer CountySolar Β· 99.0 MW Β· agreement signed
- Solar project LGE-GIS-2014-001, Mercer CountySolar Β· 10.0 MW Β· agreement signed
- Hydro project LGE-GIS-2011-005, Mercer CountyHydro Β· 6.0 MW Β· agreement signed
- Battery storage project LGE-GIS-2023-003, Mercer CountyBattery storage Β· 125 MW Β· in study
- Solar project LGE-GIS-2024-004, Mercer CountySolar Β· 22.0 MW Β· in study
- Gas project LGE-GIS-2011-004, Mercer CountyGas Β· 880 MW Β· withdrawn
- Gas project LGE-GIS-2022-011, Mercer CountyGas Β· 660 MW Β· withdrawn
- Gas project LGE-GIS-2022-004, Mercer CountyGas Β· 660 MW Β· withdrawn
- Gas project LGE-GIS-2021-006, Mercer CountyGas Β· 635 MW Β· withdrawn
- Other project G004, Mercer CountyOther Β· 174 MW Β· withdrawn
- Battery storage project LGE-GIS-2023-001, Mercer CountyBattery storage Β· 125 MW Β· withdrawn