United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Queue requests in study in the USA (2021 requests) โ€” page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown616153.0 GW
Active in queue227.7 GW896 requests
Agreement signed73.3 GW270 requests
Withdrawn2,149339.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

616 requests ยท page 6 of 13
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project AH2-025, Fountain County
Solar + storage
200 MWIn study Fountain, INPJM Oct 2021target 2027
Battery storage project Q409, Maricopa County
Battery storage
200 MWIn study Maricopa, AZWest Sep 2021target 2025
Battery storage project Company 202, Clark County
Battery storage
200 MWPaused / redesign Clark, NVWest Sep 2021target 2024
Fairboro Solar
Solar
200 MWIn study Ware, GASoutheast Dec 2021target 2023
Solar project J1870, Tangipahoa Parish County
Solar
200 MWIn study Tangipahoa Parish, LAMISO Aug 2021target 2028
Solar + storage project LGE-GIS-2021-009, Hardin County
Solar + storage
200 MWPaused / redesign Hardin, KYSoutheast Mar 2021target 2026
Solar + storage project Company LZ, Eureka County
Solar + storage
200 MWPaused / redesign Eureka, NVWest Sep 2021target 2025
Onshore wind project J1701, Mcdonough County
Onshore wind
200 MWIn study Mcdonough, ILMISO Dec 2021target 2026
Solar + storage project Company MK, Lyon County
Solar + storage
200 MWPaused / redesign Lyon, NVWest Sep 2021target 2029
Other project 110, Pima County
Other ยท TEP
200 MWIn study Pima, AZWest Dec 2021target 2024
Solar + storage project AH2-043, Kanawha County
Solar + storage
200 MWIn study Kanawha, WVPJM Nov 2021target 2025
Onshore wind project J2250, Stutsman County
Onshore wind
200 MWIn study Stutsman, NDMISO Nov 2021target 2024
Merlin Storage
Battery storage
200 MWIn study Los Angeles, CACAISO Apr 2021target 2032
Battery storage project AH2-051, New Castle County
Battery storage
200 MWIn study New Castle, DEPJM Dec 2021target 2025
Solar project J2224, Iberville Parish County
Solar
200 MWIn study Iberville Parish, LAMISO Aug 2021target 2025
Solar + storage project G0694, Crook County
Solar + storage
200 MWIn study Crook, ORWest Sep 2021target 2025
Solar project J1943, Columbia County
Solar
200 MWIn study Columbia, WIMISO Aug 2021target 2024
Solar + storage project J2153, Ashley County
Solar + storage
200 MWIn study Ashley, ARMISO Aug 2021target 2027
Battery storage project J1902, Wayne County
Battery storage
200 MWIn study Wayne, MIMISO Aug 2021target 2024
Solar project J2075, Liberty County
Solar
200 MWIn study Liberty, TXMISO Aug 2021target 2028
Solar project J2002, Washington County
Solar
200 MWIn study Washington, IAMISO Aug 2021target 2024
Battery storage project 11, Sacramento County
Battery storage
200 MWIn study Sacramento, CAWest Apr 2021target 2026
Battery storage project 100, Pierce County
Battery storage
200 MWPaused / redesign Pierce, WAWest Apr 2021target 2028
Solar + storage project Q425, Yuma County
Solar + storage
200 MWIn study Yuma, AZWest Sep 2021target 2024
Solar + storage project J1891, Attala County
Solar + storage
200 MWIn study Attala, MSMISO Aug 2021target 2027
Solar project J2228, Concordia Parish County
Solar
200 MWIn study Concordia Parish, LAMISO Dec 2021target 2027
Battery storage project J1898, Olmsted County
Battery storage
200 MWIn study Olmsted, MNMISO Aug 2021target 2024
Solar project J1849, Hardin County
Solar
200 MWIn study Hardin, TXMISO Nov 2021target 2028
Battery storage project Q422, Navajo County
Battery storage
200 MWIn study Navajo, AZWest Sep 2021target 2025
Solar project J2298, Greene County
Solar
200 MWIn study Greene, ARMISO Nov 2021target 2028
Solar + storage project Company LC, Lander County
Solar + storage
200 MWPaused / redesign Lander, NVWest Mar 2021target 2029
Battery storage project J1894, Kalamazoo County
Battery storage
200 MWIn study Kalamazoo, MIMISO Oct 2021target 2024
Other project 109, Pima County
Other ยท TEP
200 MWIn study Pima, AZWest Dec 2021target 2024
Solar + storage project Company LY, Eureka County
Solar + storage
200 MWPaused / redesign Eureka, NVWest Sep 2021target 2025
Battery storage project J1900, Wayne County
Battery storage
200 MWIn study Wayne, MIMISO Aug 2021target 2024
Solar project J2078, Story County
Solar
200 MWIn study Story, IAMISO Aug 2021target 2025
NY125B - Two Rivers Solar
Solar ยท Two Rivers Solar Farm, LLC
200 MWIn study St. Lawrence, NYNYISO May 2021target 2028
Other project 609, Sweetwater County
Other ยท NextEra Energy Resources Interconnection Holdings, LLC
200 MWPaused / redesign Sweetwater, WYWest Jun 2021target 2025
Solar project J2134, Grant County
Solar
200 MWIn study Grant, ARMISO Nov 2021target 2024
Other project 108, Pima County
Other ยท TEP
200 MWIn study Pima, AZWest Dec 2021target 2024
Solar + storage project J1846, Renville County
Solar + storage
200 MWIn study Renville, MNMISO Jul 2021target 2024
Solar + storage project Company 207, Clark County
Solar + storage
200 MWPaused / redesign Clark, NVWest Sep 2021target 2025
Solar project J2033, Clay County
Solar
200 MWIn study Clay, ILMISO Aug 2021target 2024
Battery storage project GEN-2021-040, Cass County
Battery storage
200 MWIn study Cass, NESPP Apr 2021target 2029
Battery storage project GEN-2021-038, Titus County
Battery storage
200 MWIn study Titus, TXSPP Apr 2021target 2028
Battery storage project 103, Skagit County
Battery storage
200 MWPaused / redesign Skagit, WAWest Apr 2021target 2028
Solar + storage project Company LE, Pershing County
Solar + storage
200 MWPaused / redesign Pershing, NVWest Mar 2021target 2029
Solar + storage project C1-20, Linn County
Solar + storage ยท Muddy Creek Energy Park LLC
199 MWPaused / redesign Linn, ORWest May 2021target 2025
Onshore wind project GI-DISIS-2021-07, Prowers County
Onshore wind
199 MWPaused / redesign Prowers, COWest May 2021target 2026
Solar + storage project C1-37, Kittitas County
Solar + storage ยท Badger Gap PV I, LLC
199 MWPaused / redesign Kittitas, WAWest May 2021target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)