SOLAR + STORAGE · WEST

Solar + storage project G0694, Crook County

Solar + storage project G0694, Crook County is a 200 MW solar + storage request in interconnection study in the West interconnection queue, in Crook County, Oregon.

Queue statusIn planning
  1. PlanningQueued Sep 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
G0694
Grid region
West (non-ISO utilities)
Connection point (POI)
Ponderosa Substation 500 kV
Location
Crook County, Oregon
Technology
Solar: 100 MW · Battery: 100 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
22 September 2021
Proposed online date
December 2025

Location

Marker shows the centre of Crook County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Crook County