Solar + storage project Q425, Yuma County

Solar + storage project Q425, Yuma County is a 200 MW solar + storage request in interconnection study in the West interconnection queue, in Yuma County, Arizona, connecting to Arizona Public Service.

Queue statusIn planning
  1. PlanningQueued Sep 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q425
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
Orchard 230kV
Location
Yuma County, Arizona
Technology
Solar: 200 MW · Battery
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
Transitional Cluster: Cluster Study (Phase 2 - Results Meeting)
Queue status
Active
Entered queue
30 September 2021
Proposed online date
December 2024

Location

Marker shows the centre of Yuma County; the queue data does not give exact sites.