Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown47276.1 GW
Active in queue24.3 GW251 requests
Agreement signed860 MW7 requests
Withdrawn47276.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

472 requests · page 6 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 442, Manatee County
Solar · FPL
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast Mar 2022target 2026
Solar project 271, Sumter County
Solar · Masked
74.5 MWWithdrawn / abandoned Sumter, FLSoutheast Nov 2019target 2022
Solar project 578, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2029
Solar project 470, Desoto County
Solar · FPL
74.5 MWWithdrawn / abandoned Desoto, FLSoutheast Jul 2022target 2027
Solar project 581, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2030
Solar + storage project 354, Putnam County
Solar + storage · Third Party
74.5 MWWithdrawn / abandoned Putnam, FLSoutheast Jul 2018target 2023
Solar project 575, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2028
Solar project 24
Solar
74.5 MWWithdrawn / abandoned FLSoutheast Oct 2018target 2020
Solar project 5, Manatee County
Solar
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast Apr 2017target 2020
Solar project 483, Highlands County
Solar · FPL
74.5 MWWithdrawn / abandoned Highlands, FLSoutheast Jul 2022target 2026
Solar project 263, Hardee County
Solar · Zolfo Springs Solar, LLC
74.5 MWWithdrawn / abandoned Hardee, FLSoutheast Jul 2019target 2022
Solar project 481, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2022target 2028
Solar project 10, Manatee County
Solar
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast Apr 2017target 2020
Solar + storage project 330, Flagler County
Solar + storage · Third Party
74.5 MWWithdrawn / abandoned Flagler, FLSoutheast Jan 20182023
Solar project 17
Solar
74.5 MWWithdrawn / abandoned FLSoutheast May 2016target 2019
Solar project 588, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2032
Solar project 327, Putnam County
Solar · Third Party
74.5 MWWithdrawn / abandoned Putnam, FLSoutheast Sep 20172021
Solar project IC-714, Gadsden County
Solar
74.5 MWWithdrawn / abandoned Gadsden, FLSoutheast Jun 2018
Osceola Solar 2
Solar
74.5 MWWithdrawn / abandoned Osceola, FLSoutheast Nov 2017
Solar project 217, Madison County
Solar · Masked
74.5 MWWithdrawn / abandoned Madison, FLSoutheast Feb 2018target 2020
Solar project 200, Alachua County
Solar · Masked
74.5 MWWithdrawn / abandoned Alachua, FLSoutheast Oct 2017target 2019
Solar project 203A, Osceola County
Solar · Masked
74.5 MWWithdrawn / abandoned Osceola, FLSoutheast Nov 2017target 2020
Solar project 241, Alachua County
Solar · Masked
74.5 MWWithdrawn / abandoned Alachua, FLSoutheast Nov 2018target 2020
Solar project 225, Levy County
Solar · Florida Renewable Partners, LLC
74.5 MWWithdrawn / abandoned Levy, FLSoutheast Apr 2018target 2021
Solar project 488, Highlands County
Solar · FPL
74.5 MWWithdrawn / abandoned Highlands, FLSoutheast Jul 2022target 2028
Solar project 360, Nassau County
Solar · FPL
74.5 MWWithdrawn / abandoned Nassau, FLSoutheast Sep 2018target 2025
Solar project 21, Polk County
Solar
74.5 MWWithdrawn / abandoned Polk, FLSoutheast Apr 2017target 2019
Solar project 573, Charlotte County
Solar · FPL
74.5 MWWithdrawn / abandoned Charlotte, FLSoutheast Jul 2023target 2029
Solar project 7, Manatee County
Solar
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast Apr 2017target 2020
Solar project 264, Hardee County
Solar · Mae Meadows Solar, LLC
74.5 MWWithdrawn / abandoned Hardee, FLSoutheast Jul 2019target 2022
Solar project IC-744, Calhoun County
Solar
74.5 MWWithdrawn / abandoned Calhoun, FLSoutheast Oct 2018
Solar project 577, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2029
Solar project 69, Polk County
Solar
74.5 MWWithdrawn / abandoned Polk, FLSoutheast Apr 2020target 2023
Solar project 265, Hamilton County
Solar · Masked
74.5 MWWithdrawn / abandoned Hamilton, FLSoutheast Aug 2019target 2021
Solar project 167, Hamilton County
Solar · Masked
74.5 MWWithdrawn / abandoned Hamilton, FLSoutheast Dec 2016target 2018
Solar project 582, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2030
Solar project 68, Polk County
Solar
74.5 MWWithdrawn / abandoned Polk, FLSoutheast Apr 2020target 2023
Solar project 487, Highlands County
Solar · FPL
74.5 MWWithdrawn / abandoned Highlands, FLSoutheast Jul 2022target 2028
Solar project 57, Hillsborough County
Solar
74.5 MWWithdrawn / abandoned Hillsborough, FLSoutheast Apr 2019target 2021
Solar project 102, Hillsborough County
Solar
74.5 MWWithdrawn / abandoned Hillsborough, FLSoutheast Apr 2023target 2025
Solar project 4, Polk County
Solar
74.5 MWWithdrawn / abandoned Polk, FLSoutheast Apr 2017target 2020
Solar project 583, Okeechobee County
Solar · FPL
74.5 MWWithdrawn / abandoned Okeechobee, FLSoutheast Jul 2023target 2031
Solar project 468, Madison County
Solar · Third Party
74.5 MWWithdrawn / abandoned Madison, FLSoutheast Jul 2022target 2026
Solar project 485, Highlands County
Solar · FPL
74.5 MWWithdrawn / abandoned Highlands, FLSoutheast Jul 2022target 2027
Solar project 484, Highlands County
Solar · FPL
74.5 MWWithdrawn / abandoned Highlands, FLSoutheast Jul 2022target 2026
Osceola Solar 1
Solar
74.5 MWWithdrawn / abandoned Osceola, FLSoutheast Nov 2017
Solar project 598, Gadsden County
Solar · Third Party
74.5 MWWithdrawn / abandoned Gadsden, FLSoutheast Sep 2023target 2027
Solar project 207, Osceola County
Solar · Poinsett Solar, LLC
74.5 MWWithdrawn / abandoned Osceola, FLSoutheast Dec 2017target 2023
Solar project 73, Polk County
Solar
74.5 MWWithdrawn / abandoned Polk, FLSoutheast Apr 2020target 2023
Solar project 26, Pasco County
Solar
74.5 MWWithdrawn / abandoned Pasco, FLSoutheast Apr 2017target 2020
Page 6 of 10

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)