Solar project 575, Okeechobee County

Solar project 575, Okeechobee County is a 74.5 MW solar request withdrawn in the Southeast interconnection queue, in Okeechobee County, Florida, connecting to Florida Power & Light.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
575
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Florida Power & Light
Developer
FPL
Connection point (POI)
State Road 70
Location
Okeechobee County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
25 July 2023
Proposed online date
January 2028

Location

Marker shows the centre of Okeechobee County; the queue data does not give exact sites.

Power plants in Florida Β· Transmission lines in Florida

Other requests in Okeechobee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem