United States › Grid › Interconnection queues › Arkansas

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Arkansas — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown32457.8 GW
Active in queue35.4 GW157 requests
Agreement signed1,783 MW13 requests
Withdrawn32457.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

324 requests · page 5 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J3788, Grant County
Solar
100 MWWithdrawn / abandoned Grant, ARMISO Apr 2024target 2028
Battery storage project J2978, Crittenden County
Battery storage
100 MWWithdrawn / abandoned Crittenden, ARMISO Sep 2022target 2026
Solar project J1147, St. Francis County
Solar
100 MWWithdrawn / abandoned St. Francis, ARMISO Mar 2018target 2021
Solar project J3531, White County
Solar
100 MWWithdrawn / abandoned White, ARMISO Apr 2024target 2027
Solar project J1443, Union County
Solar
100 MWWithdrawn / abandoned Union, ARMISO Apr 2019target 2023
Battery storage project J2223, Jackson County
Battery storage
100 MWWithdrawn / abandoned Jackson, ARMISO Dec 2021target 2024
Solar project J681, Jackson County
Solar
100 MWWithdrawn / abandoned Jackson, ARMISO Jul 2016target 2018
Solar project J3099, Faulkner County
Solar
100 MWWithdrawn / abandoned Faulkner, ARMISO Sep 2022target 2027
Solar project J2141, Monroe County
Solar
100 MWWithdrawn / abandoned Monroe, ARMISO Sep 2021target 2024
Battery storage project J2522, Mississippi County
Battery storage
100 MWWithdrawn / abandoned Mississippi, ARMISO Sep 2022target 2026
Solar project J902, Ashley County
Solar
100 MWWithdrawn / abandoned Ashley, ARMISO Jun 2017target 2019
Solar project J2111, Crittenden County
Solar
100 MWWithdrawn / abandoned Crittenden, ARMISO Aug 2021target 2025
Solar project J2110, Crittenden County
Solar
100 MWWithdrawn / abandoned Crittenden, ARMISO Aug 2021target 2025
Solar project J3578, Greene County
Solar
100 MWWithdrawn / abandoned Greene, ARMISO Apr 2024target 2027
Battery storage project J2460, Jefferson County
Battery storage
100 MWWithdrawn / abandoned Jefferson, ARMISO Sep 2022target 2026
Solar project J621, Lincoln County
Solar
100 MWWithdrawn / abandoned Lincoln, ARMISO May 2016target 2018
Solar project J2630, Woodruff County
Solar
100 MWWithdrawn / abandoned Woodruff, ARMISO Sep 2022target 2025
Solar project J3191, Jackson County
Solar
100 MWWithdrawn / abandoned Jackson, ARMISO Sep 2022target 2025
Solar project J677, Cross County
Solar
100 MWWithdrawn / abandoned Cross, ARMISO Jul 2016target 2016
Solar project J3034, Monroe County
Solar
100 MWWithdrawn / abandoned Monroe, ARMISO Sep 2022target 2026
Solar project J904, Ashley County
Solar
100 MWWithdrawn / abandoned Ashley, ARMISO Jun 2017target 2019
Battery storage project GEN-2023-213, Benton County
Battery storage
100 MWWithdrawn / abandoned Benton, ARSPP Oct 2023target 2028
Solar + storage project J2126, Lonoke County
Solar + storage
100 MWWithdrawn / abandoned Lonoke, ARMISO Aug 2021target 2024
Solar project J666, Crittenden County
Solar
100 MWWithdrawn / abandoned Crittenden, ARMISO Jul 2016target 2019
Solar project J922, Chicot County
Solar
100 MWWithdrawn / abandoned Chicot, ARMISO Jun 2017target 2020
Solar project J2299, Greene County
Solar
100 MWWithdrawn / abandoned Greene, ARMISO Sep 2021target 2025
Solar + storage project J3061, Lawrence County
Solar + storage
100 MWWithdrawn / abandoned Lawrence, ARMISO Sep 2022target 2025
Battery storage project J2597, Crittenden County
Battery storage
100 MWWithdrawn / abandoned Crittenden, ARMISO Sep 2022target 2026
Solar project J948, Poinsett County
Solar
100 MWWithdrawn / abandoned Poinsett, ARMISO Jun 2017target 2020
Solar project J684, Pulaski County
Solar
100 MWWithdrawn / abandoned Pulaski, ARMISO Jul 2016target 2019
Solar project J2941, Chicot County
Solar
100 MWWithdrawn / abandoned Chicot, ARMISO Sep 2022target 2025
Solar project J678, St. Francis County
Solar
100 MWWithdrawn / abandoned St. Francis, ARMISO Jul 2016target 2018
Solar project GEN-2024-006, Lawrence County
Solar
100 MWWithdrawn / abandoned Lawrence, ARSPP Apr 2024target 2029
Gas project GEN-2000-001, Jackson County
Gas
100 MWWithdrawn / abandoned Jackson, ARSPP
Solar project J3675, Greene County
Solar
100 MWWithdrawn / abandoned Greene, ARMISO Apr 2024target 2029
Battery storage project J3164, Ouachita County
Battery storage
100 MWWithdrawn / abandoned Ouachita, ARMISO Sep 2022target 2026
Battery storage project J2528, Crittenden County
Battery storage
100 MWWithdrawn / abandoned Crittenden, ARMISO Sep 2022target 2026
Solar project J617, Lincoln County
Solar
100 MWWithdrawn / abandoned Lincoln, ARMISO May 2016target 2019
Solar project J2755, Pike County
Solar
100 MWWithdrawn / abandoned Pike, ARMISO Sep 2022target 2025
Solar project J1280, Monroe County
Solar
100 MWWithdrawn / abandoned Monroe, ARMISO Apr 2019target 2022
Battery storage project J2517, Lee County
Battery storage
100 MWWithdrawn / abandoned Lee, ARMISO Sep 2022target 2026
Solar project J3868, Sharp County
Solar
100 MWWithdrawn / abandoned Sharp, ARMISO Dec 2024target 2029
Solar project J1134, White County
Solar
100 MWWithdrawn / abandoned White, ARMISO Mar 2018target 2021
Solar + storage project J2072, Grant County
Solar + storage
100 MWWithdrawn / abandoned Grant, ARMISO Aug 2021target 2024
Solar project J3588, Lawrence County
Solar
100 MWWithdrawn / abandoned Lawrence, ARMISO Apr 2024target 2028
Solar project J1137, Jackson County
Solar
100 MWWithdrawn / abandoned Jackson, ARMISO Mar 2018target 2021
Solar project J3193, Hot Spring County
Solar
100 MWWithdrawn / abandoned Hot Spring, ARMISO Sep 2022target 2025
Battery storage project J2412, Pulaski County
Battery storage
100 MWWithdrawn / abandoned Pulaski, ARMISO Sep 2022target 2026
Battery storage project J2458, Conway County
Battery storage
100 MWWithdrawn / abandoned Conway, ARMISO Sep 2022target 2026
Solar project J822, Lonoke County
Solar
100 MWWithdrawn / abandoned Lonoke, ARMISO Jun 2017target 2019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)