SOLAR Β· MISOSolar project J904, Ashley County
Solar project J904, Ashley County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Ashley County, Arkansas, connecting to Entergy.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2017 (completed)
- Withdrawn / abandonedJan 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J904
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Entergy
- Connection point (POI)
- Hamburg - Mist 115kV Line
- Location
- Ashley County, Arkansas
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 16 June 2017
- Proposed online date
- September 2019
- Withdrawn
- January 2019
Location
Marker shows the centre of Ashley County; the queue data does not give exact sites.
Other requests in Ashley County
- Solar project J680, Ashley CountySolar Β· 100 MW Β· under construction
- Solar project J603, Ashley CountySolar Β· 100 MW Β· agreement signed
- Solar project J1281, Ashley CountySolar Β· 75.0 MW Β· agreement signed
- Solar + storage project J2153, Ashley CountySolar + storage Β· 200 MW Β· in study
- Battery storage project J3614, Ashley CountyBattery storage Β· 180 MW Β· withdrawn
- Solar project J3613, Ashley CountySolar Β· 180 MW Β· withdrawn
- Solar project J902, Ashley CountySolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem