United States βΊ Grid βΊ Interconnection queues βΊ Arkansas
SOLAR Β· MISOSolar project J3675, Greene County
Solar project J3675, Greene County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Greene County, Arkansas, connecting to OTTER TAIL POWER COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2024 (completed)
- Withdrawn / abandonedSep 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3675
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- OTTER TAIL POWER COMPANY
- Connection point (POI)
- SEDGEWICK SS - AECC LIGHT 115.0kV
- Location
- Greene County, Arkansas
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Withdrawn
- Entered queue
- 18 April 2024
- Proposed online date
- September 2029
- Withdrawn
- September 2025
Location
Marker shows the centre of Greene County; the queue data does not give exact sites.
Other requests in Greene County
- Solar project J2298, Greene CountySolar Β· 200 MW Β· in study
- Solar project J4035, Greene CountySolar Β· 113 MW Β· withdrawn
- Solar project J3578, Greene CountySolar Β· 100 MW Β· withdrawn
- Solar project J2299, Greene CountySolar Β· 100 MW Β· withdrawn
- Battery storage project J2300, Greene CountyBattery storage Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem