SOLAR + STORAGE Β· MISO

Solar + storage project J2126, Lonoke County

Solar + storage project J2126, Lonoke County is a 100 MW solar + storage request withdrawn in the MISO interconnection queue, in Lonoke County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedAug 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2126
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
Garner SS to Seracy Price 115kV line
Location
Lonoke County, Arkansas
Technology
Solar: 100 MW Β· Battery
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process
Queue status
Withdrawn
Entered queue
25 August 2021
Proposed online date
April 2024
Withdrawn
August 2024

Location

Marker shows the centre of Lonoke County; the queue data does not give exact sites.