United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

SOLAR Β· MISO

Solar project J2909, Lonoke County

Solar project J2909, Lonoke County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Lonoke County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2909
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
Remington AECC to Lonoke E 115kV
Location
Lonoke County, Arkansas
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
14 September 2022
Proposed online date
June 2027
Withdrawn
March 2023

Location

Marker shows the centre of Lonoke County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Lonoke County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem