πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

SOLAR Β· MISO

Solar project J1991, Lonoke County

Solar project J1991, Lonoke County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Lonoke County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1991
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
Genpower Keo 500kV
Location
Lonoke County, Arkansas
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
25 August 2021
Proposed online date
October 2025
Withdrawn
March 2025

Location

Marker shows the centre of Lonoke County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Lonoke County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem