United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in West (non-ISO utilities) (2025 requests) β€” page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown32584.1 GW
Active in queue84.1 GW325 requests
Agreement signed0.1 MW1 requests
Withdrawn7520.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

325 requests Β· page 5 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project T2-074, Owyhee County
Battery storage
175 MWIn study Owyhee, IDWest Sep 2025target 2027
Battery storage project T2-073, Owyhee County
Battery storage
175 MWIn study Owyhee, IDWest Sep 2025target 2027
Onshore wind project GI-2025-10, Kit Carson County
Onshore wind
175 MWIn study Kit Carson, COWest Apr 2025target 2026
Solar + storage project T2-055, Juab County
Solar + storage
175 MWIn study Juab, UTWest Sep 2025target 2029
Gas project IA-PNM-2025-20, Bernalillo County
Gas
172 MWIn study Bernalillo, NMWest Mar 2025target 2029
Gas project 758, Elmore County
Gas
167 MWIn study Elmore, IDWest Mar 2025target 2028
Solar + storage project GI-CS-2025-12, Las Animas County
Solar + storage
165 MWIn study Las Animas, COWest Sep 2025target 2029
Other project Q612, Coconino County
Other
161 MWIn study Coconino, AZWest May 2025target 2028
Battery storage project T2-080, Salt Lake County
Battery storage
160 MWIn study Salt Lake, UTWest Sep 2025target 2027
Solar + storage project T2-026, Albany County
Solar + storage
160 MWIn study Albany, WYWest Sep 2025target 2026
Gas project 25-00415, Clark County
Gas
156 MWIn study Clark, NVWest Jul 2025target 2028
Battery storage project Q2503, Maricopa County
Battery storage
155 MWIn study Maricopa, AZWest Feb 2025target 2029
Solar + storage project T2-037, Emery County
Solar + storage
150 MWIn study Emery, UTWest Sep 2025target 2028
Solar + storage project GI-CS-2025-16, Weld County
Solar + storage
150 MWIn study Weld, COWest Sep 2025target 2029
Ea150B
Battery storage
150 MWIn study El Paso, TXWest Jun 2025target 2028
Battery storage project IA-PNM-2025-13, Valencia County
Battery storage
150 MWIn study Valencia, NMWest Mar 2025target 2027
Battery storage project T2-072, Siskiyou County
Battery storage
150 MWIn study Siskiyou, CAWest Sep 2025target 2027
Solar + storage project GI-CS-2025-22, Huerfano County
Solar + storage
150 MWIn study Huerfano, COWest Sep 2025target 2030
Ve-DL-150SB
Solar + storage
150 MWIn study Dona Ana, NMWest Jun 2025target 2028
Battery storage project 25-00435, Storey County
Battery storage
150 MWIn study Storey, NVWest Jul 2025target 2029
Other project Q587, Pinal County
Other
150 MWIn study Pinal, AZWest May 2025target 2031
Solar + storage project GI-CS-2025-23, Las Animas County
Solar + storage
150 MWIn study Las Animas, COWest Sep 2025target 2030
Battery storage project GI-SISS-2025-05, Kit Carson County
Battery storage
150 MWIn study Kit Carson, COWest Aug 2025target 2027
Solar project 25-011625, Weld County
Solar
143 MWIn study Weld, COWest Jan 2025target 2026
Solar + storage project 773, Ada County
Solar + storage
130 MWIn study Ada, IDWest Apr 2025target 2030
Other project Q588, Pinal County
Other
130 MWIn study Pinal, AZWest May 2025target 2031
Other project Q614, Maricopa County
Other
125 MWIn study Maricopa, AZWest May 2025target 2027
Solar project 790, Washington County
Solar
122 MWIn study Washington, IDWest Apr 2025target 2030
Battery storage project IA-PNM-2025-12, Cibola County
Battery storage
115 MWIn study Cibola, NMWest Mar 2025target 2027
Gas project 40603, Laramie County
Gas Β· Cheyenne Light, Fuel and Power Company
115 MWIn study Laramie, WYWest Aug 2025target 2028
Gas project 40969, Laramie County
Gas Β· Cheyenne Light, Fuel and Power Company
115 MWIn study Laramie, WYWest Aug 2025target 2028
Onshore wind project G1074, Gilliam County
Onshore wind
111 MWIn study Gilliam, ORWest Feb 2025target 2027
Solar + storage project GI-CS-2025-28, Prowers County
Solar + storage
110 MWIn study Prowers, COWest Oct 2025target 2030
Gas project CS25-05, Kootenai County
Gas
102 MWIn study Kootenai, IDWest Apr 2025target 2029
Gas project CS25-04, Kootenai County
Gas
102 MWIn study Kootenai, IDWest Apr 2025target 2027
Solar project 2025-G5
Solar
100 MWIn study West Sep 2025target 2028
Battery storage project CSUT-2025-6, El Paso County
Battery storage
100 MWIn study El Paso, COWest Mar 2025target 2027
Battery storage project T2-041, Multnomah County
Battery storage
100 MWIn study Multnomah, ORWest Sep 2025target 2027
Battery storage project S0036, Emery County
Battery storage
100 MWIn study Emery, UTWest Jun 2025target 2027
Solar + storage project T2-054, Utah County
Solar + storage
100 MWIn study Utah, UTWest Sep 2025target 2027
Solar + storage project Q579, Pinal County
Solar + storage
100 MWIn study Pinal, AZWest Apr 2025target 2029
Battery storage project IA-PNM-2025-11, Valencia County
Battery storage
100 MWIn study Valencia, NMWest Mar 2025target 2028
Battery storage project CS25-03, Spokane County
Battery storage
100 MWIn study Spokane, WAWest Apr 2025target 2030
Battery storage project 25-00387, Clark County
Battery storage
100 MWIn study Clark, NVWest Jul 2025target 2031
Battery storage project CSUT-2025-8, El Paso County
Battery storage
100 MWIn study El Paso, COWest Mar 2025target 2028
Solar project CSUT-2025-2, El Paso County
Solar
100 MWIn study El Paso, COWest Mar 2025target 2028
Solar + storage project 2025-G6
Solar + storage
100 MWIn study West Oct 2025target 2028
Onshore wind project T2-022, Walla Walla County
Onshore wind
100 MWIn study Walla Walla, WAWest Sep 2025target 2026
Solar + storage project GI-CS-2025-10, Otero County
Solar + storage
100 MWIn study Otero, COWest Sep 2025target 2029
Solar + storage project T2-038, Wallowa County
Solar + storage
90.0 MWIn study Wallowa, ORWest Sep 2025target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)