United States β€Ί Grid β€Ί Interconnection queues

SOLAR Β· WEST

Solar project 2025-G5

Solar project 2025-G5 is a 100 MW solar request in interconnection study in the West interconnection queue, connecting to WAPA Rocky Mountain Region.

Queue statusIn planning
  1. PlanningQueued Sep 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
2025-G5
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA Rocky Mountain Region
Connection point (POI)
Bucknum Tap Substation 115kV
Technology
Solar: 100 MW
Total requested
100 MW
Study phase
In Progress
Queue status
Active
Entered queue
30 September 2025
Proposed online date
July 2028

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem