Withdrawn queue requests in the USA — page 460

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 460 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project AG1-077, Magoffin County
Solar + storage
3.7 MWWithdrawn / abandoned Magoffin, KYPJM Jul 2020target 2022
San Ysidro Energy Storage
Battery storage
3.7 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Solar project AG2-205, Huntingdon County
Solar
3.7 MWWithdrawn / abandoned Huntingdon, PAPJM Mar 2021target 2024
Valley 715 - EMA ASO
Solar + storage
3.7 MWWithdrawn / abandoned Plymouth, MAISO-NE Jun 2022target 2023
EE CT DER Group Study
Solar
3.7 MWWithdrawn / abandoned Litchfield, CTISO-NE May 2024target 2024
Frates
Battery storage
3.7 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
BE-Chalybeate
Solar + storage
3.7 MWWithdrawn / abandoned Bedford, PAPJM Mar 2020target 2022
BR-Mountain View
Solar + storage
3.7 MWWithdrawn / abandoned Berks, PAPJM Mar 2020target 2022
Solar project AH1-006, Essex County
Solar
3.7 MWWithdrawn / abandoned Essex, NJPJM Apr 2021target 2022
Coyote Ranch Energy Storage
Battery storage
3.7 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Onshore wind project C3-091, Albany County
Onshore wind · PacifiCorp
3.6 MWWithdrawn / abandoned Albany, WYWest May 2023target 2024
Geothermal project C4-001, Beaver County
Geothermal
3.6 MWWithdrawn / abandoned Beaver, UTWest Apr 2024target 2025
Solar plus Battery
Solar + storage
3.6 MWWithdrawn / abandoned Berkshire, MAISO-NE Sep 2021target 2022
Solar project V4-066, Atlantic County
Solar
3.6 MWWithdrawn / abandoned Atlantic, NJPJM Jan 2010target 2010
Other project AA1-063, Randolph County
Other
3.6 MWWithdrawn / abandoned Randolph, INPJM Sep 2014target 2016
Onshore wind project GI-0914, Lyon County
Onshore wind
3.6 MWWithdrawn / abandoned Lyon, MNWest May 2009target 2010
Hydro project 344, Fremont County
Hydro
3.6 MWWithdrawn / abandoned Fremont, IDWest Jun 2010target 2012
Other project Q27, Maricopa County
Other
3.6 MWWithdrawn / abandoned Maricopa, AZWest Nov 2006target 2009
Solar project AE2-002, Prince George's County
Solar
3.6 MWWithdrawn / abandoned Prince George's, MDPJM Oct 2018target 2019
Solar project AA1-096, Washington County
Solar
3.5 MWWithdrawn / abandoned Washington, MDPJM Oct 2014target 2016
Solar project AA1-093, Washington County
Solar
3.5 MWWithdrawn / abandoned Washington, MDPJM Oct 2014target 2016
Solar project V4-017, Sussex County
Solar
3.5 MWWithdrawn / abandoned Sussex, NJPJM Nov 2009target 2010
Battery storage project AF2-098, Grant County
Battery storage
3.5 MWWithdrawn / abandoned Grant, KYPJM Feb 2020target 2020
Kenyon Substation - NG Western RI DG Area Study
Solar
3.5 MWWithdrawn / abandoned Washington, RIISO-NE Mar 2020target 2021
Solar project AE2-016, Burlington County
Solar
3.5 MWWithdrawn / abandoned Burlington, NJPJM Nov 2018target 2020
Hopkins Hill - NG WRI DG Area Study #2 <5 MW
Solar
3.5 MWWithdrawn / abandoned Kent, RIISO-NE Aug 2020target 2022
Battery storage project Z2-093, Hunterdon County
Battery storage
3.5 MWWithdrawn / abandoned Hunterdon, NJPJM Apr 2014target 2014
Geothermal project 285, Gem County
Geothermal
3.5 MWWithdrawn / abandoned Gem, IDWest Mar 2009target 2010
Other project Q67, Cook County
Other
3.5 MWWithdrawn / abandoned Cook, ILPJM Jul 2006target 2007
Solar project Y1-042, Cumberland County
Solar
3.5 MWWithdrawn / abandoned Cumberland, NJPJM Mar 2012target 2014
Falmouth 933 - EMA ASO
Solar + storage
3.5 MWWithdrawn / abandoned Barnstable, MAISO-NE Jun 2022target 2023
Other project 236, Canyon County
Other
3.5 MWWithdrawn / abandoned Canyon, IDWest Apr 2008target 2009
Other project Q67B, Cook County
Other
3.5 MWWithdrawn / abandoned Cook, ILPJM Jul 2006target 2007
Gas project AF2-160, Allegheny County
Gas
3.5 MWWithdrawn / abandoned Allegheny, PAPJM Mar 2020target 2020
Solar project AA1-080, Washington County
Solar
3.5 MWWithdrawn / abandoned Washington, MDPJM Oct 2014target 2016
Solar project AA1-068, Washington County
Solar
3.5 MWWithdrawn / abandoned Washington, MDPJM Oct 2014target 2016
Solar project AE2-105, Sussex County
Solar
3.5 MWWithdrawn / abandoned Sussex, NJPJM Feb 2019target 2020
Solar project AE2-018, Mercer County
Solar
3.5 MWWithdrawn / abandoned Mercer, NJPJM Dec 2018target 2020
Solar project Y1-081, Talbot County
Solar
3.4 MWWithdrawn / abandoned Talbot, MDPJM Apr 2012target 2013
Hydro project 450, Lewis And Clark County
Hydro
3.4 MWWithdrawn / abandoned Lewis And Clark, MTWest Oct 2023target 2025
Gas project Y3-113, Wyoming County
Gas
3.4 MWWithdrawn / abandoned Wyoming, PAPJM Apr 2013target 2014
Bath 115 kV SS - Midcoast Area DG Study
Solar
3.4 MWWithdrawn / abandoned Lincoln, MEISO-NE Oct 2023target 2024
Camptonville Biopower
Other
3.4 MWWithdrawn / abandoned Yuba, CACAISO Dec 2018target 2021
Greenville Solar
Solar
3.4 MWWithdrawn / abandoned Darke, OHPJM Aug 2011target 2017
Onshore wind project GEN-2016-054, Jerauld County
Onshore wind
3.4 MWWithdrawn / abandoned Jerauld, SDSPP Mar 2016
Onshore wind project 318, Meagher County
Onshore wind
3.3 MWWithdrawn / abandoned Meagher, MTWest Jun 2017target 2018
Solar project AB1-032, Athens County
Solar
3.3 MWWithdrawn / abandoned Athens, OHPJM Jul 2015target 2016
Solar project 679, Iron County
Solar
3.3 MWWithdrawn / abandoned Iron, UTWest Jun 2015target 2016
Onshore wind project M13, Lee County
Onshore wind
3.3 MWWithdrawn / abandoned Lee, ILPJM May 2004target 2005
Onshore wind project 319, Meagher County
Onshore wind
3.3 MWWithdrawn / abandoned Meagher, MTWest Jun 2017target 2018
Page 460 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)