BATTERY STORAGE Β· PJM

Battery storage project Z2-093, Hunterdon County

Battery storage project Z2-093, Hunterdon County is a 3.5 MW battery storage request withdrawn in the PJM interconnection queue, in Hunterdon County, New Jersey, connecting to JCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2014 (completed)
  2. Withdrawn / abandonedMay 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Z2-093
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Connection point (POI)
Hawks 12kV
Location
Hunterdon County, New Jersey
Technology
Battery: 3.5 MW
Total requested
3.5 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
30 April 2014
Proposed online date
December 2014
Withdrawn
May 2014

Location

Marker shows the centre of Hunterdon County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Hunterdon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem