United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in West (non-ISO utilities) — page 45
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery storage project 133, Pima County Battery storage |
150 MW | Withdrawn / abandoned |
| Battery storage project 381, Deer Lodge County Battery storage |
150 MW | Withdrawn / abandoned |
| Solar + storage project 768, Minidoka County Solar + storage |
150 MW | Withdrawn / abandoned |
| Solar project GI20217, Puebl County Solar |
150 MW | Withdrawn / abandoned |
| Solar + storage project Company QU, Washoe County Solar + storage |
150 MW | Withdrawn / abandoned |
| Onshore wind project GI-0821, Ward County Onshore wind |
150 MW | Withdrawn / abandoned |
| Solar project Q26, Kern County Solar |
150 MW | Withdrawn / abandoned |
| Onshore wind project 172-B, Sweetwater County Onshore wind · Evergreen Wind Power Partner, LLC |
150 MW | Withdrawn / abandoned |
| Onshore wind project GI-0920, Bon Homme County Onshore wind |
150 MW | Withdrawn / abandoned |
| Solar project 321, Yellowstone County Solar |
150 MW | Withdrawn / abandoned |
| Solar project C3-087, Klamath County Solar · PacifiCorp |
150 MW | Withdrawn / abandoned |
| Battery storage project 789, Ada County Battery storage |
150 MW | Withdrawn / abandoned |
| Solar + storage project C2-201, Beaver County Solar + storage |
150 MW | Withdrawn / abandoned |
| Solar project 119, Columbia County Solar |
150 MW | Withdrawn / abandoned |
| Onshore wind project 3, Kittitas County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project 172-A, Sweetwater County Onshore wind · Evergreen Wind Power Partner, LLC |
150 MW | Withdrawn / abandoned |
| Gas project 352, Sweet Grass County Gas |
150 MW | Withdrawn / abandoned |
| Solar project IA-PNM-2017-03, Sandoval County Solar |
150 MW | Withdrawn / abandoned |
| Solar project Company 113, Clark County Solar |
150 MW | Withdrawn / abandoned |
| Touchet Wind Farm Onshore wind · Winds Over Washington Energy Group |
150 MW | Withdrawn / abandoned |
| Solar + storage project GI-2023-2, Routt County Solar + storage |
150 MW | Withdrawn / abandoned |
| Onshore wind project 306, Union County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project GI-2010-5, Logan County Onshore wind |
150 MW | Withdrawn / abandoned |
| Solar + storage project C2-135, Crook County Solar + storage |
150 MW | Withdrawn / abandoned |
| Solar + storage project Company 169, Clark County Solar + storage |
150 MW | Withdrawn / abandoned |
| Solar + storage project 744, Jerome County Solar + storage |
150 MW | Withdrawn / abandoned |
| Battery storage project 731, Ada County Battery storage |
150 MW | Withdrawn / abandoned |
| Onshore wind project Q09, Navajo County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project Q08, Navajo County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project 302, Cassia County Onshore wind |
148 MW | Withdrawn / abandoned |
| Onshore wind project G0554, Hood River County Onshore wind |
148 MW | Withdrawn / abandoned |
| Solar + storage project Q353, Pinal County Solar + storage |
145 MW | Withdrawn / abandoned |
| Onshore wind project GI-0813a, Kossuth County Onshore wind |
145 MW | Withdrawn / abandoned |
| Gas project 65, Clatsop County Gas |
145 MW | Withdrawn / abandoned |
| Solar project 684, Minidoka County Solar |
145 MW | Withdrawn / abandoned |
| Onshore wind project 13, Columbia County Onshore wind · PacifiCorp Commercial & Trading |
140 MW | Withdrawn / abandoned |
| Gas project IA-PNM-2007-05, Bernalillo Cty County Gas |
140 MW | Withdrawn / abandoned |
| Solar project 686, Blaine County Solar |
140 MW | Withdrawn / abandoned |
| Solar + storage project Q253, Pinal County Solar + storage |
140 MW | Withdrawn / abandoned |
| Onshore wind project Company EO, Lassen County Onshore wind |
140 MW | Withdrawn / abandoned |
| Onshore wind project 130, Garfield County Onshore wind |
140 MW | Withdrawn / abandoned |
| Battery storage project Q97, Maricopa County Battery storage |
140 MW | Withdrawn / abandoned |
| Solar project 680, Twin Falls County Solar |
140 MW | Withdrawn / abandoned |
| Onshore wind project 126, Garfield County Onshore wind |
140 MW | Withdrawn / abandoned |
| Onshore wind project 2017-G4 Onshore wind |
140 MW | Withdrawn / abandoned |
| Onshore wind project 2018-G1 Onshore wind |
140 MW | Withdrawn / abandoned |
| Onshore wind project 115, Columbia County Onshore wind |
140 MW | Withdrawn / abandoned |
| Solar + storage project 678, Power County Solar + storage |
140 MW | Withdrawn / abandoned |
| Geothermal project G0214, Deschutes County Geothermal |
140 MW | Withdrawn / abandoned |
| Onshore wind project GI-2013-7, Logan County Onshore wind |
140 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)