Withdrawn queue requests in West (non-ISO utilities) — page 45

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 45 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 133, Pima County
Battery storage
150 MWWithdrawn / abandoned Pima, AZWest Jul 2022target 2025
Battery storage project 381, Deer Lodge County
Battery storage
150 MWWithdrawn / abandoned Deer Lodge, MTWest Jun 2020target 2023
Solar + storage project 768, Minidoka County
Solar + storage
150 MWWithdrawn / abandoned Minidoka, IDWest Apr 2025
Solar project GI20217, Puebl County
Solar
150 MWWithdrawn / abandoned Puebl, COWest Mar 2021target 2022
Solar + storage project Company QU, Washoe County
Solar + storage
150 MWWithdrawn / abandoned Washoe, NVWest Mar 2024target 2027
Onshore wind project GI-0821, Ward County
Onshore wind
150 MWWithdrawn / abandoned Ward, NDWest Jul 2008target 2011
Solar project Q26, Kern County
Solar
150 MWWithdrawn / abandoned Kern, CAWest Mar 2012target 2015
Onshore wind project 172-B, Sweetwater County
Onshore wind · Evergreen Wind Power Partner, LLC
150 MWWithdrawn / abandoned Sweetwater, WYWest Nov 2007target 2013
Onshore wind project GI-0920, Bon Homme County
Onshore wind
150 MWWithdrawn / abandoned Bon Homme, SDWest Jul 2009target 2011
Solar project 321, Yellowstone County
Solar
150 MWWithdrawn / abandoned Yellowstone, MTWest Jun 2017target 2019
Solar project C3-087, Klamath County
Solar · PacifiCorp
150 MWWithdrawn / abandoned Klamath, ORWest May 2023target 2029
Battery storage project 789, Ada County
Battery storage
150 MWWithdrawn / abandoned Ada, IDWest Apr 2025
Solar + storage project C2-201, Beaver County
Solar + storage
150 MWWithdrawn / abandoned Beaver, UTWest May 2022target 2026
Solar project 119, Columbia County
Solar
150 MWWithdrawn / abandoned Columbia, WAWest Aug 2021target 2024
Onshore wind project 3, Kittitas County
Onshore wind
150 MWWithdrawn / abandoned Kittitas, WAWest Jun 2007target 2008
Onshore wind project 172-A, Sweetwater County
Onshore wind · Evergreen Wind Power Partner, LLC
150 MWWithdrawn / abandoned Sweetwater, WYWest Nov 2007target 2012
Gas project 352, Sweet Grass County
Gas
150 MWWithdrawn / abandoned Sweet Grass, MTWest Jul 2018target 2019
Solar project IA-PNM-2017-03, Sandoval County
Solar
150 MWWithdrawn / abandoned Sandoval, NMWest Jan 2017target 2020
Solar project Company 113, Clark County
Solar
150 MWWithdrawn / abandoned Clark, NVWest Nov 2011target 2015
Touchet Wind Farm
Onshore wind · Winds Over Washington Energy Group
150 MWWithdrawn / abandoned Walla Walla, WAWest Oct 2001target 2004
Solar + storage project GI-2023-2, Routt County
Solar + storage
150 MWWithdrawn / abandoned Routt, COWest May 2023target 2025
Onshore wind project 306, Union County
Onshore wind
150 MWWithdrawn / abandoned Union, ORWest Oct 2009
Onshore wind project GI-2010-5, Logan County
Onshore wind
150 MWWithdrawn / abandoned Logan, COWest Mar 2010target 2011
Solar + storage project C2-135, Crook County
Solar + storage
150 MWWithdrawn / abandoned Crook, ORWest May 2022target 2026
Solar + storage project Company 169, Clark County
Solar + storage
150 MWWithdrawn / abandoned Clark, NVWest Sep 2018target 2020
Solar + storage project 744, Jerome County
Solar + storage
150 MWWithdrawn / abandoned Jerome, IDWest Oct 2023target 2027
Battery storage project 731, Ada County
Battery storage
150 MWWithdrawn / abandoned Ada, IDWest Jul 2023target 2026
Onshore wind project Q09, Navajo County
Onshore wind
150 MWWithdrawn / abandoned Navajo, AZWest Jun 2010target 2014
Onshore wind project Q08, Navajo County
Onshore wind
150 MWWithdrawn / abandoned Navajo, AZWest Jun 2010target 2013
Onshore wind project 302, Cassia County
Onshore wind
148 MWWithdrawn / abandoned Cassia, IDWest Sep 2009
Onshore wind project G0554, Hood River County
Onshore wind
148 MWWithdrawn / abandoned Hood River, ORWest Oct 2016target 2019
Solar + storage project Q353, Pinal County
Solar + storage
145 MWWithdrawn / abandoned Pinal, AZWest Sep 2020target 2023
Onshore wind project GI-0813a, Kossuth County
Onshore wind
145 MWWithdrawn / abandoned Kossuth, IAWest Jun 2008target 2010
Gas project 65, Clatsop County
Gas
145 MWWithdrawn / abandoned Clatsop, ORWest Nov 2005target 2010
Solar project 684, Minidoka County
Solar
145 MWWithdrawn / abandoned Minidoka, IDWest Nov 2022target 2026
Onshore wind project 13, Columbia County
Onshore wind · PacifiCorp Commercial & Trading
140 MWWithdrawn / abandoned Columbia, WAWest Sep 2001target 2004
Gas project IA-PNM-2007-05, Bernalillo Cty County
Gas
140 MWWithdrawn / abandoned Bernalillo Cty, NMWest Apr 2007target 2015
Solar project 686, Blaine County
Solar
140 MWWithdrawn / abandoned Blaine, IDWest Nov 2022
Solar + storage project Q253, Pinal County
Solar + storage
140 MWWithdrawn / abandoned Pinal, AZWest Mar 2017target 2019
Onshore wind project Company EO, Lassen County
Onshore wind
140 MWWithdrawn / abandoned Lassen, CAWest Feb 2010target 2016
Onshore wind project 130, Garfield County
Onshore wind
140 MWWithdrawn / abandoned Garfield, WAWest Feb 2022target 2025
Battery storage project Q97, Maricopa County
Battery storage
140 MWWithdrawn / abandoned Maricopa, AZWest Sep 2022target 2025
Solar project 680, Twin Falls County
Solar
140 MWWithdrawn / abandoned Twin Falls, IDWest Oct 2022
Onshore wind project 126, Garfield County
Onshore wind
140 MWWithdrawn / abandoned Garfield, WAWest Sep 2021target 2025
Onshore wind project 2017-G4
Onshore wind
140 MWWithdrawn / abandoned West Apr 2017target 2020
Onshore wind project 2018-G1
Onshore wind
140 MWWithdrawn / abandoned West Nov 2017target 2020
Onshore wind project 115, Columbia County
Onshore wind
140 MWWithdrawn / abandoned Columbia, WAWest Aug 2021target 2025
Solar + storage project 678, Power County
Solar + storage
140 MWWithdrawn / abandoned Power, IDWest Oct 2022
Geothermal project G0214, Deschutes County
Geothermal
140 MWWithdrawn / abandoned Deschutes, ORWest Jan 2006target 2009
Onshore wind project GI-2013-7, Logan County
Onshore wind
140 MWWithdrawn / abandoned Logan, COWest Sep 2013target 2014
Page 45 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)