πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· WEST

Onshore wind project 2017-G4

Onshore wind project 2017-G4 is a 140 MW onshore wind request withdrawn in the West interconnection queue, connecting to WAPA Rocky Mountain Region.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2017 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2017-G4
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA Rocky Mountain Region
Connection point (POI)
Glendo - Podolak 115-kV
Technology
Wind: 140 MW
Total requested
140 MW
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
7 April 2017
Proposed online date
September 2020

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem