United States β€Ί Grid β€Ί Interconnection queues β€Ί Wyoming

ONSHORE WIND Β· WEST

Onshore wind project 172-A, Sweetwater County

Onshore wind project 172-A, Sweetwater County is a 150 MW onshore wind request withdrawn in the West interconnection queue, in Sweetwater County, Wyoming, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2007 (completed)
  2. Withdrawn / abandonedJul 2013 (project stopped here)
  3. ConsentedMar 2009 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
172-A
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Evergreen Wind Power Partner, LLC
Connection point (POI)
Firehole - Flaming Gorge
Location
Sweetwater County, Wyoming
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
IA signed 3/5/09, Suspended 7/1/10, Terminated 7/2/13
Queue status
Withdrawn
Entered queue
19 November 2007
Agreement signed
5 March 2009
Proposed online date
June 2012
Withdrawn
July 2013

Location

Marker shows the centre of Sweetwater County; the queue data does not give exact sites.

Power plants in Wyoming Β· Transmission lines in Wyoming

Other requests in Sweetwater County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem