COAL · WESTCoal project 267-A, Sweetwater County
Coal project 267-A, Sweetwater County is a 22.0 MW coal request built and operating in the West interconnection queue, in Sweetwater County, Wyoming, connecting to PacifiCorp.
Request details
- Queue ID
- 267-A
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Developer
- PacifiCorp Energy
- Connection point (POI)
- Jim Bridger Power Plant, Point of Rocks, WY
- Location
- Sweetwater County, Wyoming
- Technology
- Coal: 22.0 MW
- Total requested
- 22.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA signed June 3, 2010
- Queue status
- Operational
- Entered queue
- 13 April 2009
- Agreement signed
- 3 June 2010
- Proposed online date
- November 2015
Location
Marker shows the centre of Sweetwater County; the queue data does not give exact sites.
Other requests in Sweetwater County
- Gas project T2-034, Sweetwater CountyGas · 600 MW · in study
- Gas project T2-033, Sweetwater CountyGas · 600 MW · in study
- Solar + storage project 661, Sweetwater CountySolar + storage · 1,000 MW · suspended
- Other project 607, Sweetwater CountyOther · 300 MW · suspended
- Other project 608, Sweetwater CountyOther · 300 MW · suspended
- Other project 609, Sweetwater CountyOther · 200 MW · suspended
- Solar project 720, Sweetwater CountySolar · 80.0 MW · built
- Coal project 267-B, Sweetwater CountyCoal · 22.0 MW · built
- Coal project 267-C, Sweetwater CountyCoal · 22.0 MW · built
- Coal project 267-D, Sweetwater CountyCoal · 22.0 MW · built
- Gas project 2, Sweetwater CountyGas · 11.0 MW · built
- Onshore wind project C2-43, Sweetwater CountyOnshore wind · 600 MW · withdrawn