Solar + storage project 661, Sweetwater County

Solar + storage project 661, Sweetwater County is a 1,000 MW solar + storage request suspended in the West interconnection queue, in Sweetwater County, Wyoming, connecting to Idaho Power Company.

Queue statusPaused / redesign
  1. PlanningQueued Jun 2022 (current stage)
  2. ConsentedSep 2023 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
661
Grid region
West (non-ISO utilities)
Utility / transmission owner
Idaho Power Company
Developer
Sawtooth DevCo, LLC
Connection point (POI)
JBRG 345kV Substation
Location
Sweetwater County, Wyoming
Technology
Solar: 1,000 MW · Battery
Total requested
1,000 MW
Service type
Energy only (ERIS)
Study phase
IA Executed
Queue status
Suspended
Entered queue
16 June 2022
Agreement signed
12 September 2023
Proposed online date
December 2027

Location

Marker shows the centre of Sweetwater County; the queue data does not give exact sites.