SOLAR Β· WEST

Solar project 321, Yellowstone County

Solar project 321, Yellowstone County is a 150 MW solar request withdrawn in the West interconnection queue, in Yellowstone County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
321
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Broadview 230kV Substation
Location
Yellowstone County, Montana
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study System Impact Study Facilities Study
Queue status
Withdrawn
Entered queue
29 June 2017
Proposed online date
July 2019

Location

Marker shows the centre of Yellowstone County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Yellowstone County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem