Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 445 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project Z1-093, Sandusky County
Battery storage
6.0 MWWithdrawn / abandoned Sandusky, OHPJM Oct 2013target 2014
Solar project 957241, Chester County
Solar
6.0 MWWithdrawn / abandoned Chester, SCSoutheast Jun 2024
Purdys Run Plant
Gas
6.0 MWWithdrawn / abandoned Harrison, WVPJM Feb 2012target 2015
Gas project I05, Calvert County
Gas
6.0 MWWithdrawn / abandoned Calvert, MDPJM Apr 2002target 2003
Battery storage project 561246, Greenville County
Battery storage
6.0 MWWithdrawn / abandoned Greenville, SCSoutheast May 2022
Onshore wind project GEN-2013-004, Antelope County
Onshore wind
6.0 MWWithdrawn / abandoned Antelope, NESPP Mar 2013target 2014
Onshore wind project 257, Carbon/Albany County
Onshore wind · AES Wind Generation, Inc.
6.0 MWWithdrawn / abandoned Carbon/Albany, WYWest Jan 2009target 2010
Solar project 747, Umatilla County
Solar
6.0 MWWithdrawn / abandoned Umatilla, ORWest May 2016target 2017
Onshore wind project V1-029, Schuylkill County
Onshore wind
6.0 MWWithdrawn / abandoned Schuylkill, PAPJM Apr 2009target 2013
Solar project Y1-037
Solar
6.0 MWWithdrawn / abandoned NJPJM Mar 2012
Battery storage project Z1-063, Licking County
Battery storage
6.0 MWWithdrawn / abandoned Licking, OHPJM Sep 2013target 2016
Camden (Cinnaminson Solar) 26kV
Solar
6.0 MWWithdrawn / abandoned Burlington, NJPJM Jan 2013target 2015
Other project 523, Utah County
Other
6.0 MWWithdrawn / abandoned Utah, UTWest Oct 2013target 2015
Ivanpah 1- Expansion
Solar
6.0 MWWithdrawn / abandoned San Bernardino, CACAISO Jul 2009target 2012
Onshore wind project G608, Pope County
Onshore wind
6.0 MWWithdrawn / abandoned Pope, MNMISO Mar 2006target 2006
Other project R41, Cumberland County
Other
6.0 MWWithdrawn / abandoned Cumberland, PAPJM Nov 2006target 2008
Solar project X2-051
Solar
6.0 MWWithdrawn / abandoned OHPJM Jun 2011
Linden Generating Station
Gas
6.0 MWWithdrawn / abandoned Union, NJPJM Feb 20132015
Solar project C3-044, Caribou County
Solar · PacifiCorp
6.0 MWWithdrawn / abandoned Caribou, IDWest May 2023target 2028
Gas project AH1-229, Louisa County
Gas
6.0 MWWithdrawn / abandoned Louisa, VAPJM Sep 2021target 2025
Gas project 531, Minidoka County
Gas
6.0 MWWithdrawn / abandoned Minidoka, IDWest Apr 2018
Solar
Solar
6.0 MWWithdrawn / abandoned Tolland, CTISO-NE Jun 2020target 2024
Kce NY 25, LLC
Battery storage · KCE NY 25, LLC
6.0 MWWithdrawn / abandoned Ontario, NYNYISO Nov 2021
Other project AC1-179, Sussex County
Other
6.0 MWWithdrawn / abandoned Sussex, DEPJM Oct 2016target 2019
Solar project AA1-127, Caroline County
Solar
6.0 MWWithdrawn / abandoned Caroline, MDPJM Oct 2014target 2016
Solar project 897, Klamath County
Solar
6.0 MWWithdrawn / abandoned Klamath, ORWest Jun 2017target 2019
Solar project AG2-091, Somerset County
Solar · Neptune Solar LLC
6.0 MWWithdrawn / abandoned Somerset, PAPJM Mar 2025target 2023
Other project AA1-007, Roanoke County
Other
6.0 MWWithdrawn / abandoned Roanoke, VAPJM Jun 2014target 2016
Gas project Z1-114, York County
Gas
6.0 MWWithdrawn / abandoned York, PAPJM Oct 2013target 2015
Oblong Storage
Battery storage · Invenergy Storage Development LLC
6.0 MWWithdrawn / abandoned Dutchess, NYNYISO Jan 2020
Solar
Solar
6.0 MWWithdrawn / abandoned Bristol, MAISO-NE Mar 2011target 2012
Onshore wind project K10, Somerset County
Onshore wind
6.0 MWWithdrawn / abandoned Somerset, PAPJM Jul 2003target 2005
Gas project 217, Lincoln County
Gas
6.0 MWWithdrawn / abandoned Lincoln, WYWest May 2008target 2008
Pawling BESS
Battery storage · Saturn Energy Storage LLC
6.0 MWWithdrawn / abandoned Dutchess, NYNYISO Jan 2020
Solar project X1-023, St. Mary's County
Solar
6.0 MWWithdrawn / abandoned St. Mary's, MDPJM Feb 2011target 2012
Bristol Energy Storage
Battery storage · JERA Americas Inc.
6.0 MWWithdrawn / abandoned Ontario, NYNYISO Jan 2020
Gas project 29, Bonner County
Gas
6.0 MWWithdrawn / abandoned Bonner, IDWest Jul 2010target 2012
Solar project X1-083, Salem County
Solar
6.0 MWWithdrawn / abandoned Salem, NJPJM Apr 2011target 2012
Onshore wind project G817, Grant County
Onshore wind
5.9 MWWithdrawn / abandoned Grant, MNMISO Jul 2007
Other project J152, White County
Other
5.9 MWWithdrawn / abandoned White, INMISO Jun 2010target 2010
Onshore wind project G778, Grant County
Onshore wind
5.9 MWWithdrawn / abandoned Grant, MNMISO Mar 2007target 2009
Solar project X1-007, Burlington County
Solar
5.8 MWWithdrawn / abandoned Burlington, NJPJM Feb 2011target 2011
Little Rest Rd Substation - NG WMA Group 3
Solar + storage
5.8 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Gas project 77, Salt Lake County
Gas
5.8 MWWithdrawn / abandoned Salt Lake, UTWest Apr 2006target 2007
Solar project AH1-411, Warren County
Solar
5.8 MWWithdrawn / abandoned Warren, NJPJM Sep 2021target 2022
Solar project Y3-101, Ocean County
Solar
5.7 MWWithdrawn / abandoned Ocean, NJPJM Apr 2013target 2014
Terra Gen Dixie Valley Expansion
Geothermal
5.6 MWWithdrawn / abandoned Churchill, NVCAISO Jul 2010target 2011
Middlesex Plant
Gas
5.6 MWWithdrawn / abandoned Middlesex, NJPJM Oct 2014target 2016
Solar project V2-011, Northumberland County
Solar
5.6 MWWithdrawn / abandoned Northumberland, PAPJM Jun 2009target 2010
Putnam Pike Substation - NG Western RI DG Area Study
Solar
5.6 MWWithdrawn / abandoned Providence, RIISO-NE Mar 2020target 2021
Page 445 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)