SOLAR · CAISO

Ivanpah 1- Expansion

Ivanpah 1- Expansion is a 6.0 MW solar request withdrawn in the CAISO interconnection queue, in San Bernardino County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2009 (completed)
  2. Withdrawn / abandonedNov 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
497
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
New Ivanpah Substation 115kV
Location
San Bernardino County, California
Technology
Solar: 6.0 MW
Total requested
6.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 July 2009
Proposed online date
March 2012
Withdrawn
November 2010

Location

Marker shows the centre of San Bernardino County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Bernardino County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem