OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 402

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 402 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AF2-021, Ocean County
Battery storage · Calpine Mid-Atlantic Development, LLC
20.0 MWWithdrawn / abandoned Ocean, NJPJM Nov 2019target 2021
Solar project J303, Murray County
Solar
20.0 MWWithdrawn / abandoned Murray, MNMISO Nov 2013target 2016
Manchester Solar
Solar · Manchester Solar NY LLC
20.0 MWWithdrawn / abandoned Ontario, NYNYISO Sep 2024
ELP Rotterdam Solar
Solar · ELP Rotterdam Solar LLC
20.0 MWWithdrawn / abandoned Schenectady, NYNYISO Jun 2020
Solar project Q158, Yuma County
Solar
20.0 MWWithdrawn / abandoned Yuma, AZWest Jul 2010target 2012
Battery Storage
Battery storage
20.0 MWWithdrawn / abandoned Hartford, CTISO-NE Feb 2018target 2022
Solar project 56, Adams County
Solar
20.0 MWWithdrawn / abandoned Adams, WAWest May 2018target 2019
Onshore wind project G0248, Cassia County
Onshore wind
20.0 MWWithdrawn / abandoned Cassia, IDWest Nov 2006target 2007
Graham Solar Farm I Expansion
Solar
20.0 MWWithdrawn / abandoned Fresno, CACAISO Mar 2011target 2013
Solar project AE1-017, Pulaski County
Solar
20.0 MWWithdrawn / abandoned Pulaski, VAPJM May 2018target 2020
Warthan Creek Solar Project
Solar
20.0 MWWithdrawn / abandoned Fresno, CACAISO Mar 2011target 2013
Solar project Q115, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Mar 2010target 2012
Solar project AG2-530, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Mar 2021target 2024
El Peco Solar Farm
Solar
20.0 MWWithdrawn / abandoned Fresno, CACAISO Mar 2010target 2014
Solar project IC-626, Bleckley County
Solar
20.0 MWWithdrawn / abandoned Bleckley, GASoutheast Apr 2017
Solar project W1-044, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Mar 2010target 2011
Baird North II Wind
Onshore wind · BMP Wind LLC
20.0 MWWithdrawn / abandoned Callahan, TXERCOT Apr 2020target 2021
Solar project Q118, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Mar 2010target 2013
Battery storage project AA1-104, Gloucester County
Battery storage
20.0 MWWithdrawn / abandoned Gloucester, NJPJM Oct 2014target 2017
Solar project AD1-096, Ogle County
Solar
20.0 MWWithdrawn / abandoned Ogle, ILPJM Sep 2017target 2018
Battery storage project GEN-2015-043, Pratt County
Battery storage
20.0 MWWithdrawn / abandoned Pratt, KSSPP Oct 2015target 2017
Solar project AG2-174, Carbon County
Solar
20.0 MWWithdrawn / abandoned Carbon, PAPJM Feb 2021target 2024
Solar + storage project AG2-538, Elk County
Solar + storage · EL-Jakes Hollow LLC
20.0 MWWithdrawn / abandoned Elk, PAPJM Mar 2021target 2022
Solar project Q136, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Apr 2010target 2012
Solar
Solar
20.0 MWWithdrawn / abandoned Grafton, NHISO-NE Aug 2017target 2019
Southampton Battery Storage
Battery storage · LI Energy Storage System
20.0 MWWithdrawn / abandoned Suffolk, NYNYISO Mar 2015
Solar project Q166, Cochise County
Solar
20.0 MWWithdrawn / abandoned Cochise, AZWest Oct 2010target 2011
Solar project 436, Power County
Solar
20.0 MWWithdrawn / abandoned Power, IDWest Oct 2014
Solar project AC2-086, Clermont County
Solar
20.0 MWWithdrawn / abandoned Clermont, OHPJM Feb 2017target 2019
Vea Homestead
Solar
20.0 MWWithdrawn / abandoned Nye, NVCAISO Apr 2012target 2014
Solar project AF1-135, Clearfield County
Solar
20.0 MWWithdrawn / abandoned Clearfield, PAPJM Sep 2019target 2022
Darby Solar
Solar · Conti Enterprises, Inc.
20.0 MWWithdrawn / abandoned Washington, NYNYISO Jan 2017
State Route 26 Solar
Solar · Genesee River Solar
20.0 MWWithdrawn / abandoned Cortland, NYNYISO Sep 2024
Fork Valley Solar
Solar · Fork Valley Solar LLC
20.0 MWWithdrawn / abandoned Steuben, NYNYISO Nov 2016
Solar project AG2-002, Morrow County
Solar
20.0 MWWithdrawn / abandoned Morrow, OHPJM Oct 2020target 2023
Onshore wind project G663, Lincoln County
Onshore wind
20.0 MWWithdrawn / abandoned Lincoln, MNMISO Aug 2006target 2010
Warfield II
Solar
20.0 MWWithdrawn / abandoned Burlington, NJPJM Sep 2010target 2015
Solar project 465, Bingham County
Solar
20.0 MWWithdrawn / abandoned Bingham, IDWest Jan 2015
World Sun PV Project
Solar
20.0 MWWithdrawn / abandoned Stanislaus, CACAISO May 2010target 2011
Solar project Q176, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Jan 2011target 2012
Solar
Solar
20.0 MWWithdrawn / abandoned Franklin, VTISO-NE Apr 2018target 2021
Solar project Q130, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Apr 2010target 2012
Windy Hill Solar
Onshore wind · OneEnergy Development, LLC
20.0 MWWithdrawn / abandoned Washington, NYNYISO Feb 2015
Solar project IC-383, Mitchell County
Solar
20.0 MWWithdrawn / abandoned Mitchell, GASoutheast Jun 2014
Rosamond Solar Facility
Solar
20.0 MWWithdrawn / abandoned Kern, CACAISO May 2010target 2013
San Joaquin 2B
Solar
20.0 MWWithdrawn / abandoned Fresno, CACAISO Mar 2011target 2013
Onshore wind project 136, Deer Lodge County
Onshore wind
20.0 MWWithdrawn / abandoned Deer Lodge, MTWest Apr 2011target 2012
Machias Solar
Solar · Machias Solar, LLC
20.0 MWWithdrawn / abandoned Cattaraugus, NYNYISO Jun 2018
Whitely - Greene Battery Storage Facility
Battery storage
20.0 MWWithdrawn / abandoned Greene, PAPJM Oct 2015target 2019
Solar project AE1-187, Adams County
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Sep 2018target 2021
Page 402 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)