πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

SOLAR Β· PJM

Solar project AG2-174, Carbon County

Solar project AG2-174, Carbon County is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Carbon County, Pennsylvania, connecting to PPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-174
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PPL
Connection point (POI)
Jack Frost-Lake Harmony 69 kV
Location
Carbon County, Pennsylvania
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
26 February 2021
Proposed online date
December 2024
Withdrawn
December 2024

Location

Marker shows the centre of Carbon County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Carbon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem