Solar + storage project AG2-538, Elk County

Solar + storage project AG2-538, Elk County is a 20.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Elk County, Pennsylvania, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedFeb 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-538
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Developer
EL-Jakes Hollow LLC
Connection point (POI)
Ridgeway - Motion Control 46 kV
Location
Elk County, Pennsylvania
Technology
Solar: 20.0 MW Β· Battery
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
31 March 2021
Proposed online date
October 2022
Withdrawn
February 2025

Location

Marker shows the centre of Elk County; the queue data does not give exact sites.