Withdrawn queue requests in Arkansas — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown32457.8 GW
Active in queue35.4 GW157 requests
Agreement signed1,783 MW13 requests
Withdrawn32457.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

324 requests · page 4 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J3038, Union County
Solar
150 MWWithdrawn / abandoned Union, ARMISO Sep 2022target 2027
Solar project J1364, Crittenden County
Solar
150 MWWithdrawn / abandoned Crittenden, ARMISO Apr 2019target 2022
Solar project J1414, Clay County
Solar
150 MWWithdrawn / abandoned Clay, ARMISO Apr 2019target 2022
Onshore wind project J1400, Crittenden County
Onshore wind
150 MWWithdrawn / abandoned Crittenden, ARMISO Apr 2019target 2021
Battery storage project GEN-2022-049, Franklin County
Battery storage
150 MWWithdrawn / abandoned Franklin, ARSPP Jun 20222025
Solar project J698, Chicot County
Solar
150 MWWithdrawn / abandoned Chicot, ARMISO Jun 2017target 2015
Battery storage project J3618, Clay County
Battery storage
150 MWWithdrawn / abandoned Clay, ARMISO Apr 2024target 2028
Battery storage project J3622, Craighead County
Battery storage
150 MWWithdrawn / abandoned Craighead, ARMISO Apr 2024target 2028
Solar + storage project J3413, Pulaski County
Solar + storage
150 MWWithdrawn / abandoned Pulaski, ARMISO Mar 2024target 2028
Solar project J1811, Independence County
Solar
150 MWWithdrawn / abandoned Independence, ARMISO Jun 2020target 2023
Solar project J1156, Crittenden County
Solar
150 MWWithdrawn / abandoned Crittenden, ARMISO Mar 2018target 2020
Solar project J2328, Lonoke County
Solar
150 MWWithdrawn / abandoned Lonoke, ARMISO Sep 2022target 2027
Solar project J3037, Union County
Solar
150 MWWithdrawn / abandoned Union, ARMISO Sep 2022target 2027
Solar project J3422, Lawrence County
Solar
145 MWWithdrawn / abandoned Lawrence, ARMISO Mar 2024target 2028
Solar project J2093, Crittenden County
Solar
144 MWWithdrawn / abandoned Crittenden, ARMISO Dec 2021target 2024
Solar + storage project J3071, St. Francis County
Solar + storage
140 MWWithdrawn / abandoned St. Francis, ARMISO Sep 2022target 2024
Solar project J858, Bradley County
Solar
140 MWWithdrawn / abandoned Bradley, ARMISO Jun 2017target 2019
Solar project J972, St. Francis County
Solar
140 MWWithdrawn / abandoned St. Francis, ARMISO Mar 2018target 2021
Onshore wind project J3814, Cross County
Onshore wind
135 MWWithdrawn / abandoned Cross, ARMISO Apr 2024target 2028
Solar project J1267, Cross County
Solar
135 MWWithdrawn / abandoned Cross, ARMISO Apr 2019target 2022
Solar project J3579, Lee County
Solar
135 MWWithdrawn / abandoned Lee, ARMISO Apr 2024target 2028
Solar project J3376, Mississippi County
Solar
130 MWWithdrawn / abandoned Mississippi, ARMISO Apr 2024target 2028
Battery storage project J2468, Union County
Battery storage
130 MWWithdrawn / abandoned Union, ARMISO Sep 2022target 2026
Solar project J1309, Arkansas County
Solar
130 MWWithdrawn / abandoned Arkansas, ARMISO Apr 2019target 2021
Solar project J2733, Lawrence County
Solar
126 MWWithdrawn / abandoned Lawrence, ARMISO Sep 2025target 2026
Solar project GEN-2018-023, Little River County
Solar
126 MWWithdrawn / abandoned Little River, ARSPP Apr 2018target 2021
Solar project J3444, Jefferson County
Solar
125 MWWithdrawn / abandoned Jefferson, ARMISO Mar 2024target 2028
Solar project J2859, Lonoke County
Solar
125 MWWithdrawn / abandoned Lonoke, ARMISO Sep 2022target 2025
Solar project J3615, Arkansas County
Solar
125 MWWithdrawn / abandoned Arkansas, ARMISO Apr 2024target 2028
Battery storage project J3616, Arkansas County
Battery storage
125 MWWithdrawn / abandoned Arkansas, ARMISO Apr 2024target 2028
Solar project J2623, Hot Spring County
Solar
125 MWWithdrawn / abandoned Hot Spring, ARMISO Sep 2022target 2027
Solar project J3790, Lee County
Solar
120 MWWithdrawn / abandoned Lee, ARMISO Apr 2024target 2028
Solar project J2240, Nevada County
Solar
120 MWWithdrawn / abandoned Nevada, ARMISO Dec 2021target 2024
Solar + storage project GEN-2024-214, Hempstead County
Solar + storage
120 MWWithdrawn / abandoned Hempstead, ARSPP Mar 2025target 2029
Solar project J4035, Greene County
Solar
113 MWWithdrawn / abandoned Greene, ARMISO Jun 2025target 2029
Battery storage project J1992, Lonoke County
Battery storage
110 MWWithdrawn / abandoned Lonoke, ARMISO Aug 2021target 2025
Solar project J942, Craighead County
Solar
107 MWWithdrawn / abandoned Craighead, ARMISO Jun 2017target 2021
Solar project J2622, Drew County
Solar
107 MWWithdrawn / abandoned Drew, ARMISO Sep 2022target 2027
Solar project J3036, Lonoke County
Solar
105 MWWithdrawn / abandoned Lonoke, ARMISO Sep 2022target 2026
Solar project J3302, Jefferson County
Solar
105 MWWithdrawn / abandoned Jefferson, ARMISO Apr 2024target 2027
Solar project J2361, Perry County
Solar
105 MWWithdrawn / abandoned Perry, ARMISO Sep 2022target 2026
Solar project J387, Independence County
Solar
103 MWWithdrawn / abandoned Independence, ARMISO Sep 2014target 2016
Solar project J386, Lonoke County
Solar
103 MWWithdrawn / abandoned Lonoke, ARMISO Sep 2014
Solar project J655, Jackson County
Solar
102 MWWithdrawn / abandoned Jackson, ARMISO Jul 2016target 2019
Solar project J656, Craighead County
Solar
102 MWWithdrawn / abandoned Craighead, ARMISO Jul 2016target 2019
Solar project J654, Arkansas County
Solar
102 MWWithdrawn / abandoned Arkansas, ARMISO Jul 2016target 2019
Onshore wind project J662, Crittenden County
Onshore wind
100 MWWithdrawn / abandoned Crittenden, ARMISO Jul 2016target 2020
Solar + storage project J2184, Monroe County
Solar + storage
100 MWWithdrawn / abandoned Monroe, ARMISO Aug 2021target 2024
Solar project J622, Lonoke County
Solar
100 MWWithdrawn / abandoned Lonoke, ARMISO May 2016target 2018
Solar project J1722, Lonoke County
Solar
100 MWWithdrawn / abandoned Lonoke, ARMISO Jun 2020target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)