United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in PJM (Mid-Atlantic, Midwest) — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown905105.4 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

905 requests · page 4 of 19
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AH1-537, Highland County
Solar · Riverlake Energy, LLC
179 MWIn study Highland, OHPJM Mar 2025target 2025
Nuclear project AH1-714, Lasalle County
Nuclear · Constellation Energy Generation, LLC
174 MWIn study Lasalle, ILPJM Apr 2025
Solar + storage project AI1-213, Elk County
Solar + storage
174 MWIn study Elk, PAPJM Sep 2022target 2024
Solar + storage project AH2-258, Kendall County
Solar + storage
172 MWIn study Kendall, ILPJM Mar 2022target 2024
Battery storage project AH2-259, Kendall County
Battery storage
172 MWIn study Kendall, ILPJM Mar 2022target 2024
Mount Storm Repower
Onshore wind · Renew Development Holdco LLC
171 MWIn study Barbour, WVPJM Jan 2025target 2025
Onshore wind project AI1-003, Huntington County
Onshore wind
170 MWIn study Huntington, INPJM Apr 2022target 2026
Battery storage project AH2-204, Stephenson County
Battery storage
170 MWIn study Stephenson, ILPJM Mar 2022target 2026
Battery storage project AI1-156, Kane County
Battery storage
170 MWIn study Kane, ILPJM Sep 2022target 2027
Courthouse Solar
Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
167 MWIn study Charlotte, VAPJM Mar 2020target 2031
Solar project AI1-148, Kankakee County
Solar
164 MWIn study Kankakee, ILPJM Sep 2022target 2026
Solar project AI2-028, Union County
Solar
160 MWIn study Union, OHPJM Dec 2022target 2026
Golden Aster Solar Energy Center
Solar
160 MWPaused / redesign Grant, INPJM Sep 2018target 2026
Erie East Energy
Battery storage
160 MWPaused / redesign Erie, PAPJM Mar 2019target 2026
Solar project AH2-338, Winnebago County
Solar
160 MWIn study Winnebago, ILPJM Mar 2022target 2027
Gas project AH1-722, Union County
Gas · Parkway Generation Operating LLC
158 MWIn study Union, NJPJM Apr 2025
Solar + storage project AH1-543, Livingston County
Solar + storage · Golden Harvest Energy, LLC
157 MWIn study Livingston, ILPJM Feb 2025target 2025
Solar project AI1-137, Warren County
Solar
155 MWIn study Warren, NJPJM Sep 2022target 2025
Battery storage project AH2-376, Whiteside County
Battery storage
153 MWIn study Whiteside, ILPJM Mar 2022target 2027
Battery storage project AI2-045, City Of Virginia Beach County
Battery storage
150 MWIn study City Of Virginia Beach, VAPJM Feb 2023target 2023
Battery storage project AH2-377, Grundy County
Battery storage
150 MWIn study Grundy, ILPJM Mar 2022target 2024
Battery storage project AI2-456, King George County
Battery storage
150 MWIn study King George, VAPJM Mar 2023target 2027
Solar project AG2-230, St. Joseph County
Solar · Dumont Solar, LLC
150 MWIn study St. Joseph, INPJM Mar 2025target 2024
Battery storage project AI2-071, Atlantic County
Battery storage
150 MWIn study Atlantic, NJPJM Feb 2023target 2027
Battery storage project AI2-001, Caroline County
Battery storage
150 MWIn study Caroline, VAPJM Oct 2022target 2028
Energy Mountain
Battery storage
150 MWPaused / redesign Bucks, PAPJM Mar 2018target 2029
Battery storage project AH2-077, Sussex County
Battery storage
150 MWIn study Sussex, DEPJM Jan 2022target 2027
Solar project AG2-176, Crawford County
Solar · Trestle Solar Farm, LLC
150 MWIn study Crawford, PAPJM Mar 2025target 2024
Solar + storage project AH2-021, Barren County
Solar + storage
150 MWIn study Barren, KYPJM Oct 2021target 2026
Aurora Battery Storage II
Battery storage · Aurora Generation, LLC
150 MWIn study ILPJM Feb 2025target 2025
Solar + storage project AI2-446, Cambria County
Solar + storage
150 MWIn study Cambria, PAPJM Mar 2023target 2027
Bowfin Solar
Solar + storage
150 MWPaused / redesign Huntington, INPJM Aug 2019target 2028
Bright Stalk Generating Facility
Onshore wind · Lexington Chenoa Wind Farm LLC
150 MWIn study Mclean, ILPJM Mar 2019target 2022
Solar project AH2-350, Cumberland County
Solar
150 MWIn study Cumberland, VAPJM Mar 2022target 2025
Solar project AG2-069, Brunswick County
Solar · Virginia Electric and Power Company
150 MWIn study Brunswick, VAPJM Feb 2025target 2025
Battery storage project AG2-288, Frederick County
Battery storage · Rockline Reliability Center LLC
150 MWIn study Frederick, VAPJM Feb 2025target 2023
Wingstem Solar Energy Farm
Solar
150 MWPaused / redesign Cass, MIPJM Sep 2018target 2025
Leaf River Wind
Onshore wind · Leaf River Wind, LLC
150 MWIn study Ogle, ILPJM Sep 2018target 2021
Battery storage project AG2-621, Beaver County
Battery storage · ACE Development Company, LLC
150 MWIn study Beaver, PAPJM Feb 2025target 2023
Battery storage project AI1-166, Cass County
Battery storage
150 MWIn study Cass, MIPJM Sep 2022target 2028
Bright Stalk Generating Facility
Solar · Lexington Chenoa Wind Farm LLC
150 MWIn study Mclean, ILPJM Mar 2020target 2022
Battery storage project AI2-002, Washington County
Battery storage
150 MWIn study Washington, VAPJM Oct 2022target 2028
Battery storage project AH1-564, Winnebago County
Battery storage · Rockford Generation, LLC
150 MWIn study Winnebago, ILPJM Mar 2025target 2025
Battery storage project AI2-070, Atlantic County
Battery storage
150 MWIn study Atlantic, NJPJM Feb 2023target 2027
Battery storage project AH2-144, King George County
Battery storage
150 MWIn study King George, VAPJM Feb 2022target 2027
Solar project AH1-040, Washington County
Solar · ACE Development Company, LLC
150 MWIn study Washington, NCPJM Feb 2025target 2025
Wild Indigo Solar
Solar
150 MWPaused / redesign Surry, VAPJM Oct 2017target 2026
Solar + storage project AH2-154, Vermillion County
Solar + storage
150 MWIn study Vermillion, INPJM Feb 2022target 2024
Solar + storage project AH2-149, Van Buren County
Solar + storage
150 MWIn study Van Buren, MIPJM Feb 2022target 2026
Solar project AG2-637, Randolph County
Solar · ACE Development Company, LLC
150 MWIn study Randolph, INPJM Mar 2025target 2025
Page 4 of 19

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)