United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2023 requests) โ€” page 32

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,063551.8 GW
Active in queue298.6 GW1,249 requests
Agreement signed34.6 GW168 requests
Withdrawn2,063551.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,063 requests ยท page 32 of 42
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project IA-PNM-2023-19, Bernalillo County
Battery storage
100 MWWithdrawn / abandoned Bernalillo, NMWest Sep 2023target 2027
Solar + storage project GEN-2023-151, Hempstead County
Solar + storage
100 MWWithdrawn / abandoned Hempstead, ARSPP Oct 2023target 2028
Solar project LGE-GIS-2023-005, Caldwell County
Solar
100 MWWithdrawn / abandoned Caldwell, KYSoutheast Jun 2023target 2026
Battery storage project 559, Montgomery County
Battery storage
100 MWWithdrawn / abandoned Montgomery, TNSoutheast Jun 2023target 2026
Solar project C3-117, Duchesne County
Solar
100 MWWithdrawn / abandoned Duchesne, UTWest May 2023target 2028
Fort Edward Solar Farm (NY53)
Solar ยท Fort Edward Solar
100 MWWithdrawn / abandoned Washington, NYNYISO Feb 2023
Solar + storage project C3-058, Carbon County
Solar + storage
100 MWWithdrawn / abandoned Carbon, UTWest May 2023target 2026
Solar + storage project C3-127, Kane County
Solar + storage
100 MWWithdrawn / abandoned Kane, UTWest May 2023target 2027
Solar + storage project GEN-2022-170, Curry County
Solar + storage
99.0 MWWithdrawn / abandoned Curry, NMSPP Feb 2023target 2026
Onshore wind project GEN-2023-012, Kingsbury County
Onshore wind
98.6 MWWithdrawn / abandoned Kingsbury, SDSPP Oct 2023target 2026
Gas project GEN-2023-062, Williams County
Gas
98.0 MWWithdrawn / abandoned Williams, NDSPP Oct 2023target 2028
Solar + storage project GEN-2023-130, Potter County
Solar + storage
96.0 MWWithdrawn / abandoned Potter, SDSPP Oct 2023target 2027
Solar + storage project 527, Haywood County
Solar + storage
95.0 MWWithdrawn / abandoned Haywood, TNSoutheast Dec 2023target 2024
Battery storage project IC-1216, Haralson County
Battery storage
95.0 MWWithdrawn / abandoned Haralson, GASoutheast Dec 2023
Solar + storage project C3-111, Caribou County
Solar + storage
95.0 MWWithdrawn / abandoned Caribou, IDWest May 2023target 2027
Solar project GEN-2022-218, Sharp County
Solar
95.0 MWWithdrawn / abandoned Sharp, ARSPP Mar 2023target 2028
Battery Storage
Battery storage
92.4 MWWithdrawn / abandoned Hampden, MAISO-NE May 2023target 2027
Jaguarundi Storage
Other ยท Jaguarundi Solar, LLC
91.1 MWWithdrawn / abandoned Archer, TXERCOT Mar 2023target 2025
Van Kleef
Gas
91.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Jaguarundi Solar
Solar ยท Jaguarundi Solar, LLC
90.3 MWWithdrawn / abandoned Archer, TXERCOT Mar 2023target 2027
Battery storage project GEN-2023-232, Benton County
Battery storage
90.0 MWWithdrawn / abandoned Benton, ARSPP Oct 20232025
Falcon Palm Energy Center
Battery storage
90.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Solar + storage project C3-042, Wallowa County
Solar + storage
90.0 MWWithdrawn / abandoned Wallowa, ORWest May 2023target 2026
Battery storage project GEN-2022-134, Roger Mills County
Battery storage
90.0 MWWithdrawn / abandoned Roger Mills, OKSPP Feb 2023target 2027
Battery storage project GEN-2022-140, Johnson County
Battery storage
90.0 MWWithdrawn / abandoned Johnson, MOSPP Feb 2023target 2027
Solar + storage project LGE-GIS-2023-004, Mercer County
Solar + storage
89.0 MWWithdrawn / abandoned Mercer, KYSoutheast May 2023target 2027
Solar project 207, Marlboro County
Solar
88.2 MWWithdrawn / abandoned Marlboro, SCSoutheast Jun 2023target 2057
Solar project 898445, Marlboro County
Solar ยท Masked
88.2 MWWithdrawn / abandoned Marlboro, SCSoutheast Jun 2023
Kama 3 FPV
Solar + storage
87.8 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Ridgeview Energy Storage
Battery storage
85.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Solar + storage project GEN-2023-074, Rosebud County
Solar + storage
85.0 MWWithdrawn / abandoned Rosebud, MTSPP Oct 2023target 2028
Solar + storage project C3-123, Carbon County
Solar + storage
85.0 MWWithdrawn / abandoned Carbon, UTWest May 2023target 2027
Beck Storage
Battery storage ยท ACE DevCo NC, LLC
85.0 MWWithdrawn / abandoned Chautauqua, NYNYISO Nov 2023
Onshore wind project GEN-2023-147, Sioux County
Onshore wind
85.0 MWWithdrawn / abandoned Sioux, NESPP Oct 2023target 2030
Solar project GEN-2024-SR1, Chouteau County
Solar
84.0 MWWithdrawn / abandoned Chouteau, OKSPP Nov 20232025
Juniper Hybrid
Solar + storage
84.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Solar project 543, Mcnairy County
Solar
84.0 MWWithdrawn / abandoned Mcnairy, TNSoutheast Apr 2023
Little Falls Solar & BESS
Solar + storage ยท Hodson Energy Little Falls LLC
83.2 MWWithdrawn / abandoned Herkimer, NYNYISO Feb 2023
Plaugher Ranch Solar
Solar + storage
81.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Solar project 896943, Wayne County
Solar
80.0 MWWithdrawn / abandoned Wayne, NCSoutheast Jun 2023
Solar project 909227, Richmond County
Solar
80.0 MWWithdrawn / abandoned Richmond, NCSoutheast Sep 2023
Solar + storage project IC-1171, Greene County
Solar + storage
80.0 MWWithdrawn / abandoned Greene, ALSoutheast Sep 2023
Malone Energy Storage
Battery storage ยท BPUS Generation Development LLC
80.0 MWWithdrawn / abandoned Franklin, NYNYISO Nov 2023
Solar project 897025, Scotland County
Solar
80.0 MWWithdrawn / abandoned Scotland, NCSoutheast Jun 2023
Solar project IC-1131, Blount County
Solar
80.0 MWWithdrawn / abandoned Blount, ALSoutheast Mar 2023
Solar + storage project IC-1109, Mobile County
Solar + storage
80.0 MWWithdrawn / abandoned Mobile, ALSoutheast Jan 2023target 2027
Solar project 920609, Wayne County
Solar
80.0 MWWithdrawn / abandoned Wayne, NCSoutheast Sep 2023
Solar project 447, Yellowstone County
Solar
80.0 MWWithdrawn / abandoned Yellowstone, MTWest Sep 2023target 2027
Solar project 920637, Scotland County
Solar
80.0 MWWithdrawn / abandoned Scotland, NCSoutheast Sep 2023
Solar + storage project 226, Kershaw County
Solar + storage
80.0 MWWithdrawn / abandoned Kershaw, SCSoutheast Jun 2023target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)