BATTERY STORAGE · NYISO

Beck Storage

Beck Storage is a 85.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Chautauqua County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1638
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
ACE DevCo NC, LLC
Connection point (POI)
159 Moon Rd to Hartfield
Location
Chautauqua County, New York
Technology
Battery: 85.0 MW
Total requested
85.0 MW
Queue status
Withdrawn
Entered queue
16 November 2023

Location

Marker shows the centre of Chautauqua County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Chautauqua County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem