Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,738603.3 GW
Active in queue161.4 GW1,067 requests
Agreement signed37.8 GW192 requests
Withdrawn2,738603.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,738 requests · page 30 of 55
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 896799, Hoke County
Solar
80.0 MWWithdrawn / abandoned Hoke, NCSoutheast Jun 2023
Solar + storage project IC-1078, Perry County
Solar + storage
80.0 MWWithdrawn / abandoned Perry, ALSoutheast Oct 2022
Solar project IC-1080, Walker County
Solar
80.0 MWWithdrawn / abandoned Walker, ALSoutheast Oct 2022target 2026
Solar project IC-518, Coffee County
Solar
80.0 MWWithdrawn / abandoned Coffee, ALSoutheast Oct 2016
Solar project IC-326, Clay County
Solar
80.0 MWWithdrawn / abandoned Clay, GASoutheast Nov 2013
Solar project IC-501, Perry County
Solar
80.0 MWWithdrawn / abandoned Perry, ALSoutheast Sep 2016
Other project 245, Jackson County
Other
80.0 MWWithdrawn / abandoned Jackson, ALSoutheast Jan 2014
Solar + storage project IC-886, Houston County
Solar + storage
80.0 MWWithdrawn / abandoned Houston, ALSoutheast Jul 2020target 2024
Solar project IC-1157, Wilcox County
Solar
80.0 MWWithdrawn / abandoned Wilcox, ALSoutheast Jul 2023target 2028
Solar project 917677, Duplin County
Solar
80.0 MWWithdrawn / abandoned Duplin, NCSoutheast Sep 2023
Solar project 961894, Wayne County
Solar
80.0 MWWithdrawn / abandoned Wayne, NCSoutheast Sep 2024
Solar + storage project IC-924, Baldwin County
Solar + storage
80.0 MWWithdrawn / abandoned Baldwin, ALSoutheast Dec 2020target 2025
Solar project 168660, Moore County
Solar
80.0 MWWithdrawn / abandoned Moore, NCSoutheast Apr 2021
Solar project 20479, Hoke County
Solar · Masked
80.0 MWWithdrawn / abandoned Hoke, NCSoutheast Mar 2018
Solar project IC-500, Montgomery County
Solar
80.0 MWWithdrawn / abandoned Montgomery, ALSoutheast Sep 2016
Solar + storage project IC-985, Marengo County
Solar + storage
80.0 MWWithdrawn / abandoned Marengo, ALSoutheast Oct 2021
Solar project IC-748, Montgomery County
Solar
80.0 MWWithdrawn / abandoned Montgomery, ALSoutheast Oct 2018
Solar + storage project IC-937, Chambers County
Solar + storage
80.0 MWWithdrawn / abandoned Chambers, ALSoutheast Dec 2020target 2024
Solar project 25-IC-1369, Montgomery County
Solar
80.0 MWWithdrawn / abandoned Montgomery, ALSoutheast Apr 2025
Solar project IC-499, Greene County
Solar
80.0 MWWithdrawn / abandoned Greene, ALSoutheast Sep 2016
Solar project 962733, Robeson County
Solar
80.0 MWWithdrawn / abandoned Robeson, NCSoutheast Sep 2024
Solar project 568988, Scotland County
Solar
80.0 MWWithdrawn / abandoned Scotland, NCSoutheast Jun 2022
Solar project IC-1104, Walker County
Solar
80.0 MWWithdrawn / abandoned Walker, ALSoutheast Jan 2023
Solar project IC-1107, Walker County
Solar
80.0 MWWithdrawn / abandoned Walker, ALSoutheast Jan 2023
Solar project IC-725, Conecuh County
Solar
80.0 MWWithdrawn / abandoned Conecuh, ALSoutheast Aug 2018
Solar project 977265, Robeson County
Solar
80.0 MWWithdrawn / abandoned Robeson, NCSoutheast Jun 2025
Solar project 920641, Bladen County
Solar
80.0 MWWithdrawn / abandoned Bladen, NCSoutheast Sep 2023
Solar project 977271, Scotland County
Solar
80.0 MWWithdrawn / abandoned Scotland, NCSoutheast Jun 2025
Solar project 23707, Person County
Solar · Masked
80.0 MWWithdrawn / abandoned Person, NCSoutheast Jul 2018
Solar project IC-336, Dodge County
Solar
80.0 MWWithdrawn / abandoned Dodge, GASoutheast Feb 2014
Solar project 169716, Bladen County
Solar
80.0 MWWithdrawn / abandoned Bladen, NCSoutheast May 2021
Solar project IC-567, Holmes County
Solar
80.0 MWWithdrawn / abandoned Holmes, FLSoutheast Dec 2016
Solar project IC-781, Sumter County
Solar
80.0 MWWithdrawn / abandoned Sumter, ALSoutheast Mar 2019
Solar project IC-509, Mitchell County
Solar
80.0 MWWithdrawn / abandoned Mitchell, GASoutheast Oct 2016
Solar + storage project IC-970, Cherokee County
Solar + storage
80.0 MWWithdrawn / abandoned Cherokee, ALSoutheast Jun 2021
Solar project IC-670, Marengo County
Solar
80.0 MWWithdrawn / abandoned Marengo, ALSoutheast Jan 2018
Solar project IC-784, Marengo County
Solar
80.0 MWWithdrawn / abandoned Marengo, ALSoutheast Mar 2019
Solar + storage project IC-1073, Marengo County
Solar + storage
80.0 MWWithdrawn / abandoned Marengo, ALSoutheast Oct 2022target 2027
Solar + storage project IC-1150, Lowndes County
Solar + storage
80.0 MWWithdrawn / abandoned Lowndes, ALSoutheast Jul 2023
Solar project 897027, Scotland County
Solar
80.0 MWWithdrawn / abandoned Scotland, NCSoutheast Jun 2023
Solar + storage project IC-1016, Bibb County
Solar + storage
80.0 MWWithdrawn / abandoned Bibb, GASoutheast Jan 2022
Solar + storage project IC-1077, Hale County
Solar + storage
80.0 MWWithdrawn / abandoned Hale, ALSoutheast Oct 2022
Solar project 21933, Jones County
Solar · Masked
80.0 MWWithdrawn / abandoned Jones, NCSoutheast May 2018
Solar + storage project IC-835, Miller County
Solar + storage
80.0 MWWithdrawn / abandoned Miller, GASoutheast Oct 2019
Solar project 917441, Scotland County
Solar
80.0 MWWithdrawn / abandoned Scotland, NCSoutheast Sep 2023
Solar project IC-524, Marengo County
Solar
80.0 MWWithdrawn / abandoned Marengo, ALSoutheast Nov 2016
Solar project 570034, Hoke County
Solar
80.0 MWWithdrawn / abandoned Hoke, NCSoutheast Jun 2022
Solar project IC-1008, Lowndes County
Solar
80.0 MWWithdrawn / abandoned Lowndes, ALSoutheast Jan 2022
Solar project IC-1025, Montgomery County
Solar
79.9 MWWithdrawn / abandoned Montgomery, ALSoutheast Feb 2022
Solar + storage project IC-1125, Perry County
Solar + storage
79.9 MWWithdrawn / abandoned Perry, ALSoutheast Mar 2023
Page 30 of 55

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)