Solar + storage project IC-835, Miller County

Solar + storage project IC-835, Miller County is a 80.0 MW solar + storage request withdrawn in the Southeast interconnection queue, in Miller County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2019 (completed)
  2. Withdrawn / abandonedDec 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-835
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
East Bainbridge - Spring Creek (Black) 115kV Line
Location
Miller County, Georgia
Technology
Solar: 80.0 MW Β· Battery
Total requested
80.0 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
29 October 2019
Withdrawn
December 2019

Location

Marker shows the centre of Miller County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Miller County