United States βΊ Grid βΊ Interconnection queues βΊ North Carolina
SOLAR Β· SOUTHEASTSolar project 897027, Scotland County
Solar project 897027, Scotland County is a 80.0 MW solar request withdrawn in the Southeast interconnection queue, in Scotland County, North Carolina, connecting to Duke Energy Progress.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 897027
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Progress
- Connection point (POI)
- LAURINBURG - RAEFORD 230KV SUB 115KV
- Location
- Scotland County, North Carolina
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Other
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 29 June 2023
Location
Marker shows the centre of Scotland County; the queue data does not give exact sites.
Power plants in North Carolina Β· Transmission lines in North Carolina
Other requests in Scotland County
- Solar project 569632, Scotland CountySolar Β· 80.0 MW Β· under construction
- Solar project 917443, Scotland CountySolar Β· 80.0 MW Β· agreement signed
- Solar project 977889, Scotland CountySolar Β· 5.0 MW Β· in study
- Solar project 897025, Scotland CountySolar Β· 80.0 MW Β· withdrawn
- Solar project 920637, Scotland CountySolar Β· 80.0 MW Β· withdrawn
- Solar project 570092, Scotland CountySolar Β· 80.0 MW Β· withdrawn
- Solar project 171542, Scotland CountySolar Β· 80.0 MW Β· withdrawn
- Solar project 962939, Scotland CountySolar Β· 80.0 MW Β· withdrawn
- Solar project 568988, Scotland CountySolar Β· 80.0 MW Β· withdrawn
- Solar project 977271, Scotland CountySolar Β· 80.0 MW Β· withdrawn
- Solar project 917441, Scotland CountySolar Β· 80.0 MW Β· withdrawn
- Solar project 5691, Scotland CountySolar Β· 75.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem