Requests shown40758.7 GW
Active in queue34.0 GW164 requests
Agreement signed8,278 MW53 requests
Withdrawn40758.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

407 requests · page 3 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2008-058, Roosevelt County
Onshore wind
201 MWWithdrawn / abandoned Roosevelt, NMSPP Jun 2008target 2010
Solar project GEN-2024-147, Eddy County
Solar
200 MWWithdrawn / abandoned Eddy, NMSPP Mar 2025target 2029
Solar + storage project IA-PNM-2025-07, Luna County
Solar + storage
200 MWWithdrawn / abandoned Luna, NMWest Mar 2025target 2028
Onshore wind project IA-PNM-2022-04, Luna County
Onshore wind
200 MWWithdrawn / abandoned Luna, NMWest Apr 2022target 2024
Battery storage project GEN-2020-080, Quay County
Battery storage
200 MWWithdrawn / abandoned Quay, NMSPP Apr 20202025
Solar project Q178, San Juan County
Solar
200 MWWithdrawn / abandoned San Juan, NMWest Jan 2011target 2015
Onshore wind project GEN-2022-171, Curry County
Onshore wind
200 MWWithdrawn / abandoned Curry, NMSPP Feb 2023target 2026
Battery storage project GEN-2022-233, Curry County
Battery storage
200 MWWithdrawn / abandoned Curry, NMSPP Feb 2023target 2028
AL200S Project
Solar
200 MWWithdrawn / abandoned Luna, NMWest Sep 2021target 2024
CA200S PV Project
Solar
200 MWWithdrawn / abandoned Otero, NMWest Dec 2015target 2021
Solar project GEN-2023-178, Roosevelt County
Solar
200 MWWithdrawn / abandoned Roosevelt, NMSPP Oct 2023target 2026
Solar project GEN-2022-232, Curry County
Solar
200 MWWithdrawn / abandoned Curry, NMSPP Feb 2023target 2028
Other project GEN-2001-020, Curry County
Other
200 MWWithdrawn / abandoned Curry, NMSPP Jun 2001
Onshore wind project GEN-2007-001, Eddy County
Onshore wind
200 MWWithdrawn / abandoned Eddy, NMSPP Jan 2007target 2009
Solar + storage project IA-PNM-2021-14, Hidalgo County
Solar + storage
200 MWWithdrawn / abandoned Hidalgo, NMWest Jul 2021target 2024
Onshore wind project GEN-2012-019, Lea County
Onshore wind
200 MWWithdrawn / abandoned Lea, NMSPP Sep 2012target 2014
Onshore wind project GEN-2012-043, Roosevelt County
Onshore wind
200 MWWithdrawn / abandoned Roosevelt, NMSPP Sep 2012target 2015
Other project GEN-2001-021, Eddy County
Other
200 MWWithdrawn / abandoned Eddy, NMSPP Jun 2001
Solar + storage project GEN-2022-033, Chaves County
Solar + storage
200 MWWithdrawn / abandoned Chaves, NMSPP Jun 20222025
Solar project GEN-2023-184, Eddy County
Solar
200 MWWithdrawn / abandoned Eddy, NMSPP Oct 2023target 2030
Solar + storage project IA-PNM-2019-17, Bernalillo County
Solar + storage
200 MWWithdrawn / abandoned Bernalillo, NMWest Apr 2019target 2021
Solar + storage project IA-PNM-2023-24, Hidalgo County
Solar + storage
200 MWWithdrawn / abandoned Hidalgo, NMWest Sep 2023target 2028
Battery storage project IA-PNM-2023-26, Luna County
Battery storage
200 MWWithdrawn / abandoned Luna, NMWest Sep 2023target 2026
Battery storage project GEN-2024-353, Curry County
Battery storage
199 MWWithdrawn / abandoned Curry, NMSPP Mar 2025target 2030
Wind + storage project IA-PNM-2023-09, Guadalupe County
Wind + storage
199 MWWithdrawn / abandoned Guadalupe, NMWest Dec 2022target 2025
Solar + storage project IA-PNM-2023-27, San Juan County
Solar + storage
199 MWWithdrawn / abandoned San Juan, NMWest Sep 2023target 2028
Solar + storage project IA-PNM-2022-05, Mckinley County
Solar + storage
199 MWWithdrawn / abandoned Mckinley, NMWest Apr 2022target 2025
Solar + storage project GEN-2024-264, Lea County
Solar + storage
199 MWWithdrawn / abandoned Lea, NMSPP Mar 2025target 2029
Solar project IA-PNM-2018-08, Torrance County
Solar
199 MWWithdrawn / abandoned Torrance, NMWest Jul 2018target 2022
AE199SB
Solar + storage
199 MWWithdrawn / abandoned Chaves, NMWest Jun 2025target 2029
Solar + storage project IA-PNM-2021-21, Santa Fe County
Solar + storage
199 MWWithdrawn / abandoned Santa Fe, NMWest Oct 2021target 2024
Battery storage project GEN-2024-347, Eddy County
Battery storage
199 MWWithdrawn / abandoned Eddy, NMSPP Mar 2025target 2027
Solar + storage project IA-PNM-2019-20, San Juan County
Solar + storage
198 MWWithdrawn / abandoned San Juan, NMWest Apr 2019target 2022
Onshore wind project IA-PNM-2013-02, Roosevelt County
Onshore wind
198 MWWithdrawn / abandoned Roosevelt, NMWest May 2013target 2014
Solar + storage project IA-PNM-2019-16, Torrance County
Solar + storage
198 MWWithdrawn / abandoned Torrance, NMWest Apr 2019target 2024
Solar + storage project IA-PNM-2020-10, Luna County
Solar + storage
195 MWWithdrawn / abandoned Luna, NMWest Jul 2020target 2023
Solar + storage project IA-PNM-2025-03, Mckinley County
Solar + storage
195 MWWithdrawn / abandoned Mckinley, NMWest Feb 2025target 2028
Solar project GEN-2017-116, Curry County
Solar
193 MWWithdrawn / abandoned Curry, NMSPP Nov 20172024
Affordable Solar
Solar + storage
190 MWWithdrawn / abandoned Rio Arriba, NMWest Jul 2018target 2021
Solar project GEN-2020-063, Roosevelt County
Solar
184 MWWithdrawn / abandoned Roosevelt, NMSPP Apr 2020target 2026
Battery storage project GEN-2022-023, Chaves County
Battery storage
175 MWWithdrawn / abandoned Chaves, NMSPP Jun 20222025
(SolarReserve)
Solar
173 MWWithdrawn / abandoned Luna, NMWest Jul 2010target 2014
Gas project IA-PNM-2018-07, Valencia County
Gas
170 MWWithdrawn / abandoned Valencia, NMWest Jul 2018target 2022
Solar Reserve
Solar
169 MWWithdrawn / abandoned Luna, NMWest Jul 2010target 2014
Onshore wind project GEN-2005-011, Chaves County
Onshore wind
160 MWWithdrawn / abandoned Chaves, NMSPP Aug 2005target 2006
Solar project IA-PNM-2017-02, Sandoval County
Solar
150 MWWithdrawn / abandoned Sandoval, NMWest Jan 2017target 2020
Solar project GEN-2022-109, Lea County
Solar
150 MWWithdrawn / abandoned Lea, NMSPP Jan 2023target 2026
Battery storage project GEN-2019-026, Lea County
Battery storage
150 MWWithdrawn / abandoned Lea, NMSPP May 2019target 2023
Solar + storage project IA-PNM-2019-10, Mckinley County
Solar + storage
150 MWWithdrawn / abandoned Mckinley, NMWest Apr 2019target 2021
Solar project GEN-2024-011, Lea County
Solar
150 MWWithdrawn / abandoned Lea, NMSPP Dec 2023target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)