SOLAR Β· SPP

Solar project GEN-2024-011, Lea County

Solar project GEN-2024-011, Lea County is a 150 MW solar request withdrawn in the SPP interconnection queue, in Lea County, New Mexico, connecting to LCEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2023 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2024-011
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
LCEC
Connection point (POI)
Lea County 115 kV Substation
Location
Lea County, New Mexico
Technology
Solar: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 December 2023
Proposed online date
December 2026
Withdrawn
December 2025

Location

Marker shows the centre of Lea County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Lea County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem