πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

ONSHORE WIND Β· SPP

Onshore wind project GEN-2007-001, Eddy County

Onshore wind project GEN-2007-001, Eddy County is a 200 MW onshore wind request withdrawn in the SPP interconnection queue, in Eddy County, New Mexico, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2007 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2007-001
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Location
Eddy County, New Mexico
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
19 January 2007
Proposed online date
December 2009

Location

Marker shows the centre of Eddy County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Eddy County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem