ONSHORE WIND Β· SPP

Onshore wind project GEN-2012-043, Roosevelt County

Onshore wind project GEN-2012-043, Roosevelt County is a 200 MW onshore wind request withdrawn in the SPP interconnection queue, in Roosevelt County, New Mexico, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2012 (completed)
  2. Withdrawn / abandonedOct 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2012-043
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Tap Eddy County - Tolk (North of GEN-2008-022 Tap)
Location
Roosevelt County, New Mexico
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 September 2012
Proposed online date
December 2015
Withdrawn
October 2013

Location

Marker shows the centre of Roosevelt County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Roosevelt County