Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown529112.4 GW
Active in queue161.4 GW1,067 requests
Agreement signed37.8 GW192 requests
Withdrawn2,738603.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

529 requests · page 3 of 11
ProjectCapacityStatusLocationRegionQueuedOnline
Calhoun Units 1 & 2
Gas
352 MWOperating Calhoun, ALSoutheast 2023
Calhoun Units 3 & 4
Gas
352 MWOperating Southeast 2023
Other project 11
Other
350 MWOperating Southeast Jun 1998
Other project 11, Sumner County
Other
350 MWOperating Sumner, TNSoutheast Jun 1998
Other project 10, Humphreys County
Other
350 MWOperating Humphreys, TNSoutheast Jun 1998
Solar project 348A, Calhoun County
Solar · FPL
350 MWOperating Calhoun, FLSoutheast Jun 20182023
Other project 10
Other
350 MWOperating Southeast Jun 1998
Doyle
Gas
345 MWOperating Walton, GASoutheast Dec 2023
Gas project 72, Osceola County
Gas · GenOn
340 MWOperating Osceola, FLSoutheast Oct 20072009
MPC Generating (CPL Monroe)
Gas
320 MWOperating Southeast 2000
Nuclear project 15, Fairfield County
Nuclear · SCPSA/SCEG
318 MWOperating Fairfield, SCSoutheast Apr 2001target 2005
Other project 68, Kemper County
Other
316 MWOperating Kemper, MSSoutheast Oct 1999
Other project 68
Other
316 MWOperating Southeast Oct 1999
Gas project 335
Gas
314 MWOperating Southeast Feb 20182019
Gas project 336
Gas
310 MWOperating Southeast Feb 20182019
Coal project 5, Berkeley County
Coal · SCPSA
306 MWOperating Berkeley, SCSoutheast Apr 2001target 2005
Other project 59
Other
300 MWOperating Southeast Aug 1999
Other project 59, Haywood County
Other
300 MWOperating Haywood, TNSoutheast Aug 1999
Gas project 3, Polk County
Gas · Duke Energy Florida, LLC
297 MWOperating Polk, FLSoutheast Mar 19992000
Coal project 13, Georgetown County
Coal · SCPSA
295 MWOperating Georgetown, SCSoutheast Apr 2001target 2005
Coal project 9, Georgetown County
Coal · SCPSA
295 MWOperating Georgetown, SCSoutheast Apr 2001target 2005
Coal project 11, Georgetown County
Coal · SCPSA
295 MWOperating Georgetown, SCSoutheast Apr 2001target 2005
Gas project 8598, Buncombe County
Gas · Duke Energy Progress, LLC
280 MWOperating Buncombe, NCSoutheast Dec 20152019
Gas project 8597, Buncombe County
Gas · Duke Energy Progress, LLC
280 MWOperating Buncombe, NCSoutheast Dec 20152019
Gas project 19, Abbeville County
Gas · SCPSA
273 MWOperating Abbeville, SCSoutheast Apr 2001target 2004
Coal project 14, Georgetown County
Coal · SCPSA
270 MWOperating Georgetown, SCSoutheast Apr 2001target 2005
Wadley Solar
Other
260 MWOperating Jefferson, GASoutheast Jul 20202024
SR Toombs
Solar
250 MWOperating Toombs, GASoutheast Apr 2020target 2024
Hog Bayou (Calpine)
Gas
230 MWOperating Southeast 2001
Gas project 28, Pinellas County
Gas · Duke Energy Florida, LLC
223 MWOperating Pinellas, FLSoutheast Sep 20052009
Gas project 30, Pinellas County
Gas · Duke Energy Florida, LLC
223 MWOperating Pinellas, FLSoutheast Jun 20052009
Gas project 29, Pinellas County
Gas · Duke Energy Florida, LLC
223 MWOperating Pinellas, FLSoutheast Sep 20052009
Gas project 27, Pinellas County
Gas · Duke Energy Florida, LLC
223 MWOperating Pinellas, FLSoutheast Sep 20052009
LGE Walton - Monroe
Gas
220 MWOperating Walton, GASoutheast Dec 2023
Smarr (aka Rumble Road)
Gas
218 MWOperating Monroe, GASoutheast Dec 2023
Cool Springs
Solar + storage
213 MWOperating Decatur, GASoutheast 2021
Gas project 366, Broward County
Gas · FPL
209 MWOperating Broward, FLSoutheast Feb 20192022
Decatur Solar
Solar
200 MWOperating Decatur, GASoutheast Aug 20182024
Twiggs Solar
Solar
200 MWOperating Twiggs, GASoutheast 2020
Hickory Part Solar & Battery
Solar + storage
196 MWOperating Mitchell, GASoutheast 2022
Turkey Run Solar
Solar
196 MWOperating Southeast 2022
Doyle 115
Gas
195 MWOperating Southeast Dec 2023
Gas project 62, Hillsborough County
Gas
186 MWOperating Hillsborough, FLSoutheast Aug 2019target 2023
Gas project 74, Osceola County
Gas · GenOn
170 MWOperating Osceola, FLSoutheast Oct 20072009
Coal project 4, Horry County
Coal · SCPSA
170 MWOperating Horry, SCSoutheast Apr 2001target 2005
Wadley Solar
Solar
170 MWOperating Jefferson, GASoutheast Jul 20162024
Southern Oak Solar Energy Center Phase II
Solar
160 MWOperating Mitchell, GASoutheast 2020
Gas project 205
Gas
160 MWOperating Southeast Sep 20162019
Quitman II
Solar
150 MWOperating Brooks, GASoutheast 2021
Walton Discover (aka Goat Rock)
Gas
150 MWOperating Lee, GASoutheast Dec 2023
Page 3 of 11

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)