United States › Grid › Interconnection queues › Florida
SOLAR · SOUTHEASTSolar project 348A, Calhoun County
Solar project 348A, Calhoun County is a 350 MW solar request built and operating in the Southeast interconnection queue, in Calhoun County, Florida, connecting to Florida Power & Light.
Request details
- Queue ID
- 348A
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Florida Power & Light
- Developer
- FPL
- Connection point (POI)
- Smith- Sinai Cemetery 230kV line
- Location
- Calhoun County, Florida
- Technology
- Solar: 350 MW
- Total requested
- 350 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 7 June 2018
- Proposed online date
- January 2026
- Came online
- January 2023
Location
Marker shows the centre of Calhoun County; the queue data does not give exact sites.
Other requests in Calhoun County
- Solar project 489, Calhoun CountySolar · 74.5 MW · in study
- Solar project 360A, Calhoun CountySolar · 74.5 MW · built
- Solar project 366A, Calhoun CountySolar · 74.5 MW · built
- Solar project 367A, Calhoun CountySolar · 74.5 MW · built
- Solar project IC-712, Calhoun CountySolar · 350 MW · withdrawn
- Battery storage project 613, Calhoun CountyBattery storage · 300 MW · withdrawn
- Battery storage project 614, Calhoun CountyBattery storage · 200 MW · withdrawn
- Solar project IC-669, Calhoun CountySolar · 75.0 MW · withdrawn
- Solar project IC-599, Calhoun CountySolar · 74.9 MW · withdrawn
- Solar project IC-745, Calhoun CountySolar · 74.5 MW · withdrawn
- Solar project IC-744, Calhoun CountySolar · 74.5 MW · withdrawn
- Solar project IC-631, Calhoun CountySolar · 54.2 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem