🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Florida

SOLAR · SOUTHEAST

Solar project 366A, Calhoun County

Solar project 366A, Calhoun County is a 74.5 MW solar request built and operating in the Southeast interconnection queue, in Calhoun County, Florida, connecting to Florida Power & Light.

Queue statusOperating
  1. PlanningQueued Feb 2019 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJan 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
366A
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Florida Power & Light
Developer
FPL
Connection point (POI)
Smith- Sinai Cemetery 230kV line
Location
Calhoun County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
21 February 2019
Proposed online date
January 2025
Came online
January 2025

Location

Marker shows the centre of Calhoun County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Calhoun County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem