πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Florida

SOLAR Β· SOUTHEAST

Solar project IC-599, Calhoun County

Solar project IC-599, Calhoun County is a 74.9 MW solar request withdrawn in the Southeast interconnection queue, in Calhoun County, Florida, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2017 (completed)
  2. Withdrawn / abandonedSep 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-599
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Smith - Sinai Cemetary 230 kV Line
Location
Calhoun County, Florida
Technology
Solar: 74.9 MW
Total requested
74.9 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
21 February 2017
Withdrawn
September 2017

Location

Marker shows the centre of Calhoun County; the queue data does not give exact sites.

Power plants in Florida Β· Transmission lines in Florida

Other requests in Calhoun County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem