United States › Grid › Interconnection queues › Georgia
GAS · SOUTHEASTLGE Walton - Monroe
LGE Walton - Monroe is a 220 MW gas request built and operating in the Southeast interconnection queue, in Walton County, Georgia, connecting to Georgia Transmission.
Request details
- Queue ID
- GI-015
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Georgia Transmission
- Connection point (POI)
- LG&E Monroe 230 kV Substation
- Location
- Walton County, Georgia
- Technology
- Gas: 220 MW
- Total requested
- 220 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 31 December 2023
Location
Marker shows the centre of Walton County; the queue data does not give exact sites.
Other requests in Walton County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem