OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in MISO (Midcontinent) — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3,261621.9 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3,261 requests · page 3 of 66
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J244, Christian County
Gas
726 MWWithdrawn / abandoned Christian, ILMISO May 2012target 2012
Other project G048, Fond Du Lac County
Other
725 MWWithdrawn / abandoned Fond Du Lac, WIMISO Aug 2000target 2006
Gas project J353, Dickinson County
Gas
725 MWWithdrawn / abandoned Dickinson, MIMISO May 2014
Gas project J841, Saginaw County
Gas
725 MWWithdrawn / abandoned Saginaw, MIMISO Jun 2017target 2020
Gas project J240, Vermillion County
Gas
720 MWWithdrawn / abandoned Vermillion, INMISO Apr 2012target 2016
Gas project J4166, Iberville Parish County
Gas
710 MWWithdrawn / abandoned Iberville Parish, LAMISO Sep 2025target 2029
Gas project G500, Shelby County
Gas
710 MWWithdrawn / abandoned Shelby, ILMISO Feb 2005target 2005
Gas project J3330, Kenosha County
Gas
705 MWWithdrawn / abandoned Kenosha, WIMISO Apr 2024target 2028
Gas project G168, Dakota County
Gas
700 MWWithdrawn / abandoned Dakota, MNMISO Jan 2002target 2005
Gas project G591, St. Louis County
Gas
700 MWWithdrawn / abandoned St. Louis, MNMISO Jan 2006target 2007
Gas project J275, Midland County
Gas
700 MWWithdrawn / abandoned Midland, MIMISO Mar 2013target 2015
Gas project J3089, Webster County
Gas
696 MWWithdrawn / abandoned Webster, KYMISO Sep 2022target 2029
Solar project J2168, Jefferson County
Solar
693 MWWithdrawn / abandoned Jefferson, TXMISO Aug 2021target 2024
Solar project J2176, Calcasieu Parish County
Solar
680 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Aug 2021target 2025
Linn County Generating Facility
Nuclear · NextEra Energy Resources Development, LLC
676 MWWithdrawn / abandoned Linn, IAMISO Aug 2025target 2028
Gas project J248, Outagamie County
Gas
675 MWWithdrawn / abandoned Outagamie, WIMISO Jun 2012target 2013
Gas project G271, Dakota County
Gas
670 MWWithdrawn / abandoned Dakota, MNMISO Dec 2002target 2004
Gas project J215, St. Joseph County
Gas
670 MWWithdrawn / abandoned St. Joseph, INMISO Jun 2011target 2014
Gas project J1459, Calhoun County
Gas
670 MWWithdrawn / abandoned Calhoun, MIMISO Apr 2019target 2024
Gas project J1288, Vermillion County
Gas
667 MWWithdrawn / abandoned Vermillion, INMISO Apr 2019target 2023
Gas project G407, Blue Earth County
Gas
667 MWWithdrawn / abandoned Blue Earth, MNMISO Feb 2004target 2004
Other project G135, Chisago County
Other
660 MWWithdrawn / abandoned Chisago, MNMISO Sep 2001target 2004
Solar project J2595, Hinds County
Solar
650 MWWithdrawn / abandoned Hinds, MSMISO Sep 2022target 2026
Other project G236, Chisago County
Other
650 MWWithdrawn / abandoned Chisago, MNMISO Jun 2002target 2002
Coal project G529, Williamson County
Coal
650 MWWithdrawn / abandoned Williamson, ILMISO Jun 2005target 2011
Gas project J4141, Morehouse Parish County
Gas
650 MWWithdrawn / abandoned Morehouse Parish, LAMISO Oct 2025target 2030
Other project G118, Grant County
Other
650 MWWithdrawn / abandoned Grant, SDMISO Aug 2001target 2005
Other project G220, Buchanan County
Other
650 MWWithdrawn / abandoned Buchanan, IAMISO Apr 2002target 2004
Other project G028, Jefferson County
Other
650 MWWithdrawn / abandoned Jefferson, INMISO Jan 2000target 2000
Other project G027, Jefferson County
Other
650 MWWithdrawn / abandoned Jefferson, INMISO Jan 2000target 2002
Solar project J2594, Hinds County
Solar
650 MWWithdrawn / abandoned Hinds, MSMISO Sep 2022target 2026
Gas project J4111, Hot Spring County
Gas
650 MWWithdrawn / abandoned Hot Spring, ARMISO Oct 2025target 2030
Gas project G219, Johnson County
Gas
650 MWWithdrawn / abandoned Johnson, IAMISO Apr 2002target 2006
Gas project G095, Wayne County
Gas
644 MWWithdrawn / abandoned Wayne, MIMISO Jun 2001target 2003
Coal project J237, Henderson County
Coal
642 MWWithdrawn / abandoned Henderson, KYMISO Jul 2007target 2013
Other project G009, Vigo County
Other
640 MWWithdrawn / abandoned Vigo, INMISO Jul 1999
Replace 15 MW of ALTW.FPL_DAEC Unit with Battery; Duane Arnold
Other
640 MWWithdrawn / abandoned Linn, IAMISO Sep 2021target 2023
Gas project J3547, Martin County
Gas
630 MWWithdrawn / abandoned Martin, MNMISO Apr 2024target 2026
Gas project G217 CONS 111, Kent County
Gas
630 MWWithdrawn / abandoned Kent, MIMISO Dec 2001target 2007
Coal project G597, Itasca County
Coal
606 MWWithdrawn / abandoned Itasca, MNMISO Feb 2006target 2012
Onshore wind project J212, Ward County
Onshore wind
600 MWWithdrawn / abandoned Ward, NDMISO Apr 2011target 2012
Other project G129, Wapello County
Other
600 MWWithdrawn / abandoned Wapello, IAMISO Sep 2001target 2007
Onshore wind project G853, Dickey County
Onshore wind
600 MWWithdrawn / abandoned Dickey, NDMISO Sep 2007target 2013
Gas project G524, Brown County
Gas
600 MWWithdrawn / abandoned Brown, WIMISO Jun 2005target 2008
Other project G036, Wood County
Other
600 MWWithdrawn / abandoned Wood, WIMISO May 2000target 2007
Coal project G039, Sullivan County
Coal
600 MWWithdrawn / abandoned Sullivan, INMISO May 2000target 2003
Gas project G181, Buchanan County
Gas
600 MWWithdrawn / abandoned Buchanan, IAMISO Mar 2002target 2004
Coal project G581, Oliver County
Coal
600 MWWithdrawn / abandoned Oliver, NDMISO Dec 2005target 2010
Gas project J1119, Jackson County
Gas
600 MWWithdrawn / abandoned Jackson, MIMISO Mar 2018target 2021
Coal project G720, Marshall County
Coal
600 MWWithdrawn / abandoned Marshall, IAMISO Dec 2006target 2012
Page 3 of 66

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)