United States › Grid › Interconnection queues › California

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in California, CAISO — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown376148.9 GW
Active in queue148.9 GW376 requests
Agreement signed81.1 GW213 requests
Withdrawn2,050551.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

376 requests · page 3 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Lake Elsinore Advanced Pumped Storage Project
Battery storage
500 MWAgreement signed Riverside, CACAISO Jun 2005target 2028
Calvada Springs Solar
Solar + storage
500 MWAgreement signed Inyo, CACAISO Apr 2020target 2027
Goldback Solar Center
Battery storage
500 MWAgreement signed Ventura, CACAISO Apr 2019target 2026
Hawkins Solar Hybrid
Solar + storage
500 MWIn study Kern, CACAISO Apr 2020target 2027
Cantus
Solar + storage
499 MWIn study Merced, CACAISO Apr 2023target 2031
Pluot
Solar + storage
479 MWAgreement signed Kings, CACAISO May 2016target 2026
Pomegranate
Solar + storage
479 MWAgreement signed Kings, CACAISO May 2016target 2025
Big SKY Solar
Solar + storage
476 MWAgreement signed Los Angeles, CACAISO Mar 2011target 2023
Corby 2
Battery storage
476 MWIn study Solano, CACAISO Apr 2021target 2031
Shoals Energy Storage 2
Battery storage
461 MWIn study Los Angeles, CACAISO Apr 2023target 2029
Mineral King Solar
Solar + storage
430 MWIn study Tulare, CACAISO Apr 2021target 2029
Boulder Brush Hybrid
Wind + storage
420 MWIn study San Diego, CACAISO Apr 2021target 2031
Tolenas
Battery storage
417 MWIn study Solano, CACAISO Apr 2021target 2031
Whiskey Diggings
Solar
414 MWIn study Sutter, CACAISO Apr 2023target 2030
Elysian
Solar + storage
412 MWAgreement signed Fresno, CACAISO Apr 2021target 2029
Dos Palmas
Battery storage
411 MWAgreement signed San Bernardino, CACAISO Apr 2021target 2031
Shoals Energy Storage
Battery storage
409 MWAgreement signed Ventura, CACAISO Apr 2020target 2030
Solstice C
Solar + storage
408 MWIn study Fresno, CACAISO Apr 2023target 2031
Hidalgo Energy Storage
Battery storage
408 MWAgreement signed San Bernardino, CACAISO Apr 2021target 2033
Solstice D
Solar + storage
408 MWIn study Fresno, CACAISO Apr 2023target 2031
Clarkson
Solar + storage
408 MWAgreement signed Fresno, CACAISO Apr 2021target 2029
Maravillosa 1
Solar + storage
407 MWIn study Kings, CACAISO Apr 2023target 2029
Lotus Solar 2
Solar + storage
406 MWIn study Madera, CACAISO Apr 2021target 2030
Simon
Battery storage
406 MWIn study Los Angeles, CACAISO Apr 2021target 2032
Gabriel Storage
Battery storage
406 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2033
Trolley
Battery storage
406 MWAgreement signed San Bernardino, CACAISO Apr 2021target 2031
Coral Reef
Battery storage
406 MWIn study Los Angeles, CACAISO Apr 2021target 2032
Fleetwood
Battery storage
406 MWIn study Los Angeles, CACAISO Apr 2021target 2032
Marici
Battery storage
406 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2031
Tea Leaf Energy Storage
Battery storage
404 MWIn study Alameda, CACAISO Apr 2023target 2030
Dirac
Battery storage
403 MWIn study San Bernardino, CACAISO Apr 2021target 2031
Mount Laguna Wind 2
Onshore wind
400 MWAgreement signed San Diego, CACAISO May 2017target 2031
Driftwood Stella
Solar + storage
400 MWAgreement signed Kern, CACAISO May 2017target 2026
Gamay
Solar + storage
400 MWIn study Kern, CACAISO Apr 2023target 2031
Aratina Solar Center 2
Solar + storage
400 MWAgreement signed Kern, CACAISO Apr 2019target 2026
Sequoia
Solar + storage
400 MWIn study Tulare, CACAISO Apr 2020target 2031
Brushy
Battery storage
400 MWIn study Solano, CACAISO Apr 2021target 2031
Rexford 2 Solar Farm
Solar + storage
400 MWAgreement signed Tulare, CACAISO Apr 2020target 2027
Aratina Solar Center 1
Solar + storage
400 MWAgreement signed San Bernardino, CACAISO Apr 2015target 2026
Sienna Solar Farm
Solar + storage
400 MWAgreement signed San Bernardino, CACAISO Apr 2015target 2027
Comstock
Gas
398 MWIn study San Bernardino, CACAISO Apr 2023target 2028
Sonrisa
Solar + storage
384 MWAgreement signed Fresno, CACAISO May 2017target 2026
MidBishop
Solar + storage
382 MWIn study Kings, CACAISO Apr 2023target 2029
Brown Bear
Solar + storage
378 MWIn study Kings, CACAISO Apr 2023target 2029
Luna Valley Solar
Solar + storage
373 MWAgreement signed Fresno, CACAISO Apr 2015target 2028
Circinus
Solar + storage
371 MWIn study Merced, CACAISO Apr 2023target 2031
Golden Flats
Battery storage
365 MWAgreement signed Stanislaus, CACAISO Apr 2021target 2031
Espresso
Battery storage
365 MWAgreement signed Alameda, CACAISO Apr 2021target 2031
Northeast Central Valley
Battery storage
365 MWIn study San Joaquin, CACAISO Apr 2021target 2031
Jewelflower Storage
Battery storage
355 MWAgreement signed Santa Clara, CACAISO Apr 2019target 2029

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)